ZDROJOVÝ PODKLAD
Uložený text
https://www.taigamotors.com/wp-content/uploads/2024/02/SQAM_TAIGA-REV-02.pdf ↗SQAM- Rev. 02 |Page. 1
SQAM- Rev. 02 |Page. 2
Contents
1. Introduction ................................................................................................................................................................................... 3
2. Definitions, Acronyms and Abbreviations......................................................................................................................... 4
3. Basic Requirements .................................................................................................................................................................... 6
4. Supplier Approval Process....................................................................................................................................................... 8
5. Product Qualification .............................................................................................................................................................. 11
6. Process control .......................................................................................................................................................................... 18
7. Packaging and Labeling.......................................................................................................................................................... 19
8. Quality events (NC, problem solving, recalls) ............................................................................................................... 20
9. Deviation Request .................................................................................................................................................................... 21
10. Supplier Performance and Corrective Actions ............................................................................................................. 22
11. Contact List and Compliance Matrix ................................................................................................................................. 23
12. Management of Hardware and Fasteners ...................................................................................................................... 23
SQAM- Rev. 02 |Page. 3
1. Introduction
1.1. Taiga
Taiga Motors Inc (below “TAIGA”) was founded in 2015 by a group of engineers that believed there
shouldn’t exist a compromise between exhilarating powersport pursuit and sacrificing the environment. Be
it carving through powder, across lakes or along dirt trails nothing beats instant torque at your fingertips,
silent speed and fresh air.
1.2. Vision
Pioneering Off-Road Electrification
1.3. Mission
Taking on one of the most challenging vehicle segments to electrify, TAIGA has pushed the frontiers of
electric technology to achieve the extreme power, weight and thermal specifications required to outperform
the high performance but polluting 2-stroke engine. The result is the world’s first electric powertrain
designed from the ground up that is faster, more reliable, more efficient & better connected to every season,
and the first line of fully electric recreative vehicles.
1.4. Values
We seek to be a global company, recognized for its competitiveness, excellence, and innovation in off-road
vehicles, all within a framework of the highest standards of integrity. The result is the world’s first electric
snowmobile, designed based on the following values:
- Safety
- Innovation
- Customer Experience Focus
- Trust & Collaboration
- Respect & Responsibility
1.5. Approach
This manual defines the minimum quality requirements for TAIGA Suppliers or TAIGA Partners to ensure
that the product complies with TAIGA customers’ regulatory and safety requirements. These requirements
are set out according to the ISO 9001 standard and TAIGA specific requirements.
1.6. Responsibility of Suppliers
TAIGA recognizes the very important role our Suppliers have in the value we offer our customers. As an
extension of our own operations, we rely on our Suppliers to provide material, products, and services which
meet all the requirements of TAIGA products, applicable specifications, and the quality management
requirements outlined herein.
It is the responsibility of each Supplier to comply with the requirements of this Supplier Quality Assurance
Manual and associated documents referred to throughout the text unless a special agreement is made
between the TAIGA SQA coordinator and the Supplier.
SQAM- Rev. 02 |Page. 4
2. Definitions, Acronyms and Abbreviations
• The words “shall”, or “must”, indicate a mandatory requirement.
• The word “should” indicates a mandatory requirement with some flexibility allowed in the method
of compliance.
• The term "Supplier" refers to the contractual part of TAIGA’s suppliers and their subcontractors. In
some cases, the Supplier can also be the manufacturer.
Acronyms and abbreviations
ITEM DESCRIPTION
8-D Eight Discipline problem solving
AAR Appearance Approval Report
AIAG Automotive Industry Action Group
APQP Advanced Product Quality Planning
Benchmarking Improvement tool to measure performance or process against other
companies’ best practices
CAD Computer-Aided Design
Containment Immediate short-term Supplier actions
Control Plan Documented description of the process for controlling the product
Corrective Action (CA) Permanent, documented, systemic corrections to the failed processes
Cpk Process Capability Index
FAI First Article Inspection
MSA Measurement System Analysis
OEE Overall Equipment Effectiveness
D/P-FMEA Design/Process Failure Mode and Effect Analysis
Design for Simultaneous engineering process designed to optimize the relationship
Manufacturability and between design function, manufacturability, and ease of assembly.
Assembly (DFM/DFA)
Failure Modes and Systematic activities intended to recognize and evaluate the potential
Effects Analysis failure of a product, and the effects and causes of that failure, identify
(FMEA) actions that could eliminate or reduce the chance of the potential failure
occurring, and document the process.
PO Purchase Order
PM Project Management
PPAP Production Part Approval Process
R&R Repeatability and Reproducibility
SQAM- Rev. 02 |Page. 5
RPN Risk Priority Number
S/N Serial Number
SPC Statistical Process Control
Table 1: Acronyms and abbreviations
Revision History:
Revision Date Responsible Description of changes
00 2021-10-13 David Maltais First emission
01 2022-09-08 David Maltais Comment added in section 3.3 to take special
machining tolerances into account.
02 2024-02-19 David Maltais Revision of the SQLF has been updated. Section 12
added. Sections 3.2.3 and 3.2.4 requirements
modified. Root cause resolution time increased.
SQAM- Rev. 02 |Page. 6
3. Basic Requirements
Critical and Special Quality Technical
Requirements Requirements Requirements
3.1. Critical and Special Requirements
Definition
Critical Characteristics related features are designated by the presence of the symbol [CC] next to the feature
on the drawing or in a specification, to indicate that the feature has the potential to affect government, safety
and environmental regulations and/or can lead to injuries to vehicle operators, passengers, other travelers,
passers-by or maintenance personnel. If any feature of a part is considered as a critical characteristic, the
part is a critical part.
Special Characteristic related features are designated by the presence of the symbol [SC] next to the feature
on the drawing or in a specification, to indicate that it has the potential to affect product’s function.
Due to the severity of these defined characteristics, it is a requirement that they be appropriately stated and
controlled within the applicable processes.
Related Documentation
Regarding dimensional, material, test and functional requirements for product features identified as Critical
Characteristic [CC] and Special Characteristic [SC], the following requirements apply and supersede the
general requirements:
o Critical AND Special Characteristics must be clearly identified throughout the manufacturing
process and in all associated documentation such as Process FMEA, Control plans and Work
Instructions
o Capability requirements for parts identified with [CC], [SC] and [PTC] (defined in Section 6.4)
characteristics are described below:
Characteristic Requirement
Cpk ≥ 1,67 Process under statistical control
Critical Characteristic [CC]
or
• Electronic or automated poka-yoke
• Effectiveness verified once per shift
TAIGA approved action plan for achieving
process control and capability
Cpk ≥ 1,33 Process under statistical control
Special Characteristic [SC]
or
Pass Through Characteristics [PTC] • 100% inspection
(See section 6.4) • TAIGA approved action plan for achieving process
control and capability
Table 2: CC and SC management
Data records resulting from Statistical Process Control (SPC), automated checking, and inspection results
must be available for download upon request by TAIGA.
SQAM- Rev. 02 |Page. 7
3.2. Quality Requirements
3.2.1. Quality Management System Requirements
All potential Prototype Suppliers are required to have a standard Quality Management System based on the
minimum requirements of ISO 9001.
All Production Suppliers must have a Quality Management System compliant to ISO 9001 as a minimum,
with the objective of becoming IATF compliant. A copy of the valid certification must be transmitted to
TAIGA by the Supplier.
3.2.2. Conformity to Environmental Regulation
ISO 14001: TAIGA encourages Suppliers to develop a certification plan along the lines of ISO 14001
standard.
3.2.3. IMDS Requirement
Supplier is encouraged to provide an IMDS submission. Where appropriate, the supplier should indicate the
IMDS number in the Part Submission Warrant document. IMDS data must be submitted through
www.mdsystem.com (Ref TAIGA IMDS ID: 234149).
3.2.4. RoHS and REACH
RoHS and REACH compliance is required to sell products in the European Union, China, Korea and some
regions of the United States and Canada. Supplier is required to provide documentation showing
compliance with both RoHS and Reach for all components sourced by TAIGA and intended for production
vehicles. Declarations based on documents such as test reports from third party or regulatory data sheet
are acceptable.
3.3. Technical / Engineering Requirements
Supplier shall comply with all 6 requirements listed below. In the event of a conflict, the more stringent
requirement shall apply. If a conflict related to quality has mutually exclusive requirements, the order of
precedence from highest to lowest will be:
Supplier Commodity
PO or
GT&C 3D Model 2D Print Quality Specific
Contract
Manual Addendum
* For the purpose of GD&T, all dimensional information contained in the 3D model is basic and the 2D has
precedence for every feature that is driven by special machining tolerances (e.g., Press fit tolerances).
3.3.1.Technical Drawing, CAD and Geometric Tolerancing
Only products manufactured according to technical drawings approved by TAIGA will be accepted. TAIGA
technical drawings take precedence over any Supplier manufacturing drawings. Also, TAIGA 3D files
override 2D technical drawings specifications. It’s expected that the Supplier has knowledge of Geometric
Dimensioning and Tolerancing (GD&T) as per the ASME Y14.5M-2009 Standard, to provide parts that are
within the tolerances as per TAIGA 2D technical drawings. It’s the Supplier’s responsibility to demonstrate
the part’s compliance to the GD&T tolerancing requirements by using the proper measurement technique
(e.g., Coordinate measurement machine).
SQAM- Rev. 02 |Page. 8
3.3.2. Review of Technical Specifications
The objective of this process is to ensure that the Supplier has a full understanding of the technical
requirements related to the product. The Supplier must review all the technical documents, standards, and
specifications defining the product and fill the compliance matrix to confirm that each requirement is
understood and achievable. In the event where a requirement isn’t understood or achievable, an action plan
needs to be put in place. The compliance matrix shall be sent by TAIGA buyer during the RFQ process.
3.3.3. Design Validation Planning and Reporting (DVP&R)
When applicable (requested by the agreed plan), the Supplier must develop and implement a product test
plan (DVP&R) that must be reviewed and approved by TAIGA Project Representatives. Inputs for the test
plan should include: DFMEA, engineering specifications and any other TAIGA defined/supplied engineering
requirements.
3.3.4. Design Failure Mode and Effects Analysis – DFMEA
Where applicable, design responsible Suppliers must develop and maintain a DFMEA throughout the life of
the product. DFMEA inputs should include warranty issues, customer concerns, lessons learned, and
address past 8D concerns.
3.3.5. Process Failure Mode and Effects Analysis – PFMEA
A PFMEA is an absolute requirement which must be developed and maintained throughout the life of the
product. PFMEA should also include inputs such as DFMEA, warranty issues, customer concerns, lessons
learned, and past 8D concerns.
4. Supplier Approval Process
Prototype FAI and PO
Prototype
NDA, GTC, SQAM RFQ Closed PO Supplier
Supplier Delivery
active
Prototype
Documenta Visit and On- Production
Production Prototype Supplier Supplier
tion Based Site Supplier
Active Initial
Supplier Assessment
Audit Assessment active
Indirect
Supplier RFQ Closed PO PO Delivery
SQAM- Rev. 02 |Page. 9
TAIGA has defined the following “Supplier Types” for the purpose of classifying its suppliers. It is possible for a single
organization to qualify as more than one (1) Supplier Type.
TYPE Definition Examples QMS *
Manufacturer A supplier who manufactures: Catalog Items ISO9001 or
• a product which is designed by Hardware, fasteners IATF 16949
(Production or the supplier or Raw Materials
Prototype) • a generic product in accordance Chemical products ISO 26262
with industry standards and Software (Software)
specifications
Subcontractor A supplier who manufactures products TAIGA part# No specific
or performs special processes in manufacturer requiremen
(Prototype) accordance with TAIGA engineering’s Build-to-print machine t
specifications shop
Subcontractor Processing house ISO9001 or
Surface / heat IATF 16949
(Production) treatments
Casting / machining
Distributor A supplier who purchases and resells Catalog Items ISO9001
products without processing the Hardware, fasteners
(Production or materials internally (apart from re- Commercial goods
Prototype) packaging, logistics, etc.) Chemical products
Indirect A supplier providing products, parts Contractors No specific
Products or and/or services in support of TAIGA’s Tools requiremen
Services industrial activities but not to be Consumables t
installed or integrated into TAIGA’s end Supplies
(Indirect) products
Laboratory A supplier providing laboratory services Calibration ISO17025
Testing
(Indirect) Analysis
Table 3: Supplier types
* Suppliers are required to implement and maintain a registered Quality Management System (QMS) to
support all applicable elements of the international standard, as defined by the Supplier Type. QMS
certification must be achieved via an accredited Certification/Registration Body (e.g., accredited by ANAB
or another equivalent, nationally recognized accrediting body). Additional ISO14001 certification is
encouraged throughout TAIGA’s Supplier base.
4.1. Supplier Evaluation Process
TAIGA requires all Suppliers to be approved prior to the issuance of contracts. All Suppliers must be
approved by TAIGA Quality, regardless of approvals by customers or other entities.
SQAM- Rev. 02 | P a g e . 10
Prototype Supplier:
Suppliers in this family can only supply prototype parts, which are not fully qualified and are not intended
to be used in the final product (production product). A prototype product is an early sample, model, or
release of a product built to test a concept or a process. A prototype is generally used to evaluate a new
design and does not necessarily use the same material or process that will be used for the production part.
Production Supplier
Suppliers in this family can supply prototype AND production parts. They are fully qualified and are
intended to be used for final production products. A production product uses the final material and the
approved process and is approved to be used in the final version of TAIGA products once the formal
qualification process is completed.
Indirect and Service Supplier
Indirect and Service Suppliers provide TAIGA with products/services not directly related to the production
(for example: furniture, office products, detergents, facility maintenance, manpower, assurance, IT services
etc.).
4.2. Supplier Evaluation Steps
The Supplier Evaluation and Approval Process includes the following steps:
a) Potential Supplier Initial Assessment
TAIGA will request the Supplier to provide a copy of its quality management system certificate and complete
a Potential Supplier Self-Assessment (PSA) of its business and quality management system and capabilities,
providing information related to the following criteria:
• Company profile
• Management
• Environment
• Quality
• Logistics
• After market
• Competence
• Product development
• Finance
• Productivity
• Sourcing
b) Documentation Audit
Once the Potential Supplier Self-Assessment (PSA) completed, the assigned Supplier Quality Engineer will
request all the relevant documented evidence related to the criteria part of the PSA. The PSA review and
the audit of the various documents will enable the Supplier Quality Engineer to determine if the Supplier’s
quality management system meets TAIGA requirements.
c) On-Site Assessment
Generally, when a Supplier is IATF 1694 / ISO TS 16949 certified by an accredited certification body, TAIGA
will not conduct an on-site assessment of the Supplier’s quality management system against the same
criteria. However, TAIGA, due to product/process complexity or criticality, may elect to conduct on-site
assessments of Supplier products or process capabilities (Process Audit – PA). As a result, findings may be
issued.
SQAM- Rev. 02 | P a g e . 11
These assessments could include:
• Quality Management System (QMS)
• Business and Manufacturing Operations
• Continuous Improvement Initiative
• Technology Assessment
• Sub-Tier Supplier Control
4.3. Supplier Status
Based on the Supplier evaluation steps, a Supplier can be classified in one of the below statuses:
Supplier Status description:
• UNDER EVALUATION: The Supplier is under evaluation to verify if it can be part of TAIGA Supplier
panel.
• ACTIVE: The Supplier is fully qualified and is currently a partner of TAIGA in all supply chain activities.
• NBH: New Business Hold – major problems occurred and no clear action plan active to solve them.
• OBSOLETE: The Supplier is obsolete. No business possible until a new evaluation is completed.
Type Receive RFI/RFQ Proto/sample delivery Production delivery
Under Evaluation yes yes no
Active yes yes yes (*)
New Business Hold no Waiver needed yes
Obsolete no no no
Table 4: Supplier status
(*) Active Suppliers can deliver production parts only after part approval in any case
5. Product Qualification
Prototype Part
Part Delivery
CAD files and Technical
FAI and QC by Part is Accepted
Requirements
TAIGA
Production Part
APQP
CAD Files and Special Part Delivery
Process PPAP Part is
Technical Processes and QC by
Requirements (When Submission Accepted
Approval TAIGA
requested)
SQAM- Rev. 02 | P a g e . 12
5.1. Prototype Product Qualification: Documentation Approval
First Article Inspection (FAI)
As a minimum, a First Article Inspection (FAI) is required to initially qualify a prototype part/process for
Supplier approval, unless the PPAP process (below) is used instead. In the event where an IATF certified
supplier produces prototype parts, he shall submit a Level 4 PPAP package.
Furthermore, a new FAI may be requested if there is an extended gap of time since last production. The FAI
requires that all features and characteristics on the design specification and control plan be inspected and
verified prior to production1. TAIGA FAI form, or other convenient and equivalent document may be used.
5.2. Product Qualification for Production
This section defines the generic requirements for production part qualification and approval. The purpose
is to determine if all TAIGA design and specification requirements are properly understood by the Supplier
and that the manufacturing processes have the capability to consistently meet these requirements.
5.2.1. Advanced Product Quality Planning (APQP)
When requested, Supplier shall implement and develop a detailed Advanced Product Quality Plan for the
development of processes used to produce a specific part or family of part. The AIAG publication “Advanced
Product Quality Planning (APQP) and Control Plan” should be used as a reference when developing these
plans. These plans should also include the TAIGA specific requirements presented in the current document.
APQP identifies the tasks to be completed, the expected timing, assigned responsibility for completion and
the critical path.
The objective of the planning process is to deliver the project on time, at the right cost and at the highest
level of quality. The initial development of the APQP should begin upon receipt of the Request for Quotation
(RFQ). This initial plan should be included as part of the RFQ response package.
The Supplier is responsible for obtaining the latest revision of the applicable AIAG core tool reference
manuals and forms (see Applicable Documents section for where these references may be obtained).
The AIAG Core Tools Manuals are:
• Advanced Product Quality Planning (APQP) and Control Plan
• Production Part Approval Process (PPAP)
• Potential Failure Mode and Effects Analysis (FMEA)
• Measurement Systems Analysis (MSA)
• Statistical Process Control (SPC)
1
For First Article Inspection guidance, see AIAG PPAP Manual (Appendix C, D, & E) – Production Part Approval
Process (available from www.aiag.org).
SQAM- Rev. 02 | P a g e . 13
APQP Timing
Suppliers of parts supported by the APQP are required to report the project status at established intervals
during the project development. As a general rule, reviews are held prior to each of the project milestones
or drawing revision releases. Suppliers should prepare for these project review meetings by completing or
updating the APQP review template, their project plan and the project milestone dates. Suppliers can access
the APQP review templates on TAIGA website.
APQP Samples
The Supplier shall provide the samples according to the APQP timing plan agreed with TAIGA, and make
sure the samples will meet the quality requirements for each milestone.
The Supplier shall submit the APQP documents (and, eventually, the PPAP) on time as TAIGA required.
TAIGA will review the documents based on the ISO 9001, IATF 16949 or AIAG. If there is any issue or timing
delay for the APQP documents, TAIGA releases a Supplier complaint according to the risk and requires root
cause analysis and improvement report to avoid other occurrences.
5.2.2. Special Processes Documentation approval
For TAIGA, the following processes are managed as special processes as defined in the ISO 9001 standard:
Process
Surface treatment (coating, plating, etc.)
Casting
Metallurgy
Plastics
Electrics and Electronics
Adhesive
Table 5: Special processes in scope
SQAM- Rev. 02 | P a g e . 14
Supplier is responsible to follow the requirements indicated in the purchase order. All first part shipment
must be approved by TAIGA. Shipping approval must be performed as per the following steps:
• Supplier and TAIGA agree on the specific tests and components part of the test plan
• Supplier performs the final inspection on one sample part (destructive test if applicable)
• Supplier must send the test results documents to TAIGA for approval
• TAIGA will analyze the documents and will inform the Supplier if the parts can be shipped
• After the reception of the shipment approval, the Supplier can send the parts
5.2.3. Production Part Approval Process (PPAP)
The Supplier shall submit to TAIGA a Production Part Approval Process (PPAP) level 3 submission package.
The Supplier is responsible for obtaining the latest revision of the applicable AIAG core tool reference
manuals and forms).
PPAP defines the approval process for new parts, revised parts, or parts produced from new or significantly
revised production methods. The PPAP process consists of 18 elements that may be required for approval
of production level parts. The PPAP manual contains detailed information, guidelines and sample
documents useful for completing the process requirements. The Production Part Approval Process (PPAP)
demonstrates that the manufacturing process used to produce parts is fully developed, thoroughly tested,
and capable of serial production of parts conforming to the technical specifications.
Every PPAP package must be sent to QUALITY@taigamotors.ca or to the assigned Supplier Quality
representative.
Unless exempted by an approved Waiver from TAIGA, Suppliers may not ship the first batch of production
parts without an approved Part Submission Warrant (PSW) document signed by TAIGA representative.
PPAP Submission Levels
The PPAP submission requirements are normally divided into five classifications or levels, as follows:
• Level 1 – Part Submission Warrant (PSW) only, submitted to TAIGA Quality
• Level 2 – PSW with product samples and limited supporting data
• Level 3 – PSW with product samples and complete supporting data
• Level 4 – PSW and other requirements as defined by the customer
• Level 5 – PSW with product samples and complete supporting data available for review at the Supplier’s
manufacturing location
SQAM- Rev. 02 | P a g e . 15
Submission Level
Level Level Level 3 Level Level
1 2 (Default) 4 5
1 Design Record (2D Drawing) R S S * R
2 Engineering Change Documents (if any) such as R S S * R
ECO/ECP
3 Engineering Approval if required R R S * R
4 DFMEA N/A N/A N/A N/A R
5 Process Flow Diagram R R S * R
6 PFMEA R R S * R
7 Control Plan R R S * R
8 Measurement Systems Analysis (GR&R) R R S * R
9 Dimensional Report R S S * R
10 Material/Performance/Functional Test Results R S S S R
11 Initial Process Studies (Short-term Capability R R S * R
Study)
12 Qualified Laboratory Documents R R S * R
13 Appearance Approval Inspection Report S S S * R
14 Sample product R S S * R
15 Master Sample R R R * R
16 Checking Aids R R R * R
17 Customer Specific Requirement compliancy R S S S S
18 Parts Submission Warrant (PSW) S S S S S
Table 6: Documents to submit
S – The Supplier will submit documentation and retain copy of records or documentation items at appropriate locations
R – The Supplier shall retain at appropriate locations and make available to TAIGA upon request.
“*” The Supplier shall retain at appropriate location and submit to TAIGA upon request.
Elements of PPAP
Below is the list of all 18 elements accompanied by a brief description for each element:
Design Documentation
Design documentation shall include both customer and the Supplier’s drawings.
Engineering Change Documentation
If the PPAP is required due to a request for a change to a part or product, the documentation requesting the
change must be included in the PPAP package. This documentation usually consists of a copy of the
Engineering Change Notice (ECN).
(Customer) Engineering Approval
This documentation usually consists of a copy of the Engineering Change Notice (ECN), approved by the
customer engineering department.
Design Failure Mode and Effects Analysis
Design Failure Mode and Effects Analysis (DFMEA) is a cross-functional activity that examines design risks
by exploring the possible failure modes and their effects on the product or customer and their probability
to occur. The DFMEA is a living document that should be reviewed and updated on a regular basis.
SQAM- Rev. 02 | P a g e . 16
Process Flow Diagram
The Process Flow Diagram clearly describes the production process and its sequence in a graphical manner.
Process Failure Mode and Effects Analysis
Process Failure Mode and Effects Analysis (PFMEA) reviews all the steps of the production process to
identify any potential failure of a process and evaluate the risk in terms of severity, occurrence, and
probability to detect failure.
Control Plan
The Control Plan is an output from the PFMEA. The Control Plan lists all product Critical and Special
Characteristics and inspection methods required to deliver products that continually meet the customer
quality requirements.
Measurement System Analysis Studies
Measurement System Analysis (MSA) studies include Gage Repeatability & Reproducibility (R&R) studies
on measurement equipment used during assembly or quality control checks. Calibration records for all
gages and measurement equipment must be included.
Dimensional Results
Each dimension on the drawing is measured on the final assembly to make sure that it falls within
specification. The results are recorded in a spreadsheet and included within the PPAP submission, a total of
5 units must be included in the dimensional report. For tooled parts, a total of 5 units per cavity is required.
Records of Material / Performance Tests
This element should contain a copy of the Design Verification Plan and Report (DVP&R). The DVP&R is a
summary of every validation test performed on the part. It should list each test performed and its result.
This section shall also include material certificate when applicable.
Initial Process Studies
Initial process studies include Statistical Process Control (SPC) charts for the Critical and Special
Characteristics of the product. These studies must demonstrate that the critical processes are stable, have
normal variation and are running near the intended nominal value.
Qualified Laboratory Documentation
Qualified laboratory documentation consists of the industry certifications for any inhouse or outsourced
lab that was involved in completing validation testing.
Appearance Approval Report
The Appearance Approval Report (AAR) is applicable for components affecting appearance only. This report
validates that the final product appearance requirements are as per specifications. Requirements include
but are not limited to color, grain, textures, etc.
Sample Production Parts
Sample production parts are sent to the customer for approval and are typically stored at either the
customer or Supplier’s site. A picture of the production part is usually included in the PPAP documentation
along with documentation regarding the part location.
Master Sample
A master sample is a final sample of the product that is inspected and signed off by the customer. The master
sample part is used to train operators and serves as a benchmark for comparison to standard production
parts if any quality questions arise.
SQAM- Rev. 02 | P a g e . 17
Checking Aids
This is a detailed list of checking aids used by production. It should include all tools used to inspect, test or
measure parts during the assembly process. The list should describe the tool and have its calibration
schedule. Checking aids may include check fixtures, contour, variable and attribute gages, models, or
templates. MSA may be required for all checking aids based on customer requirements.
Customer Specific Requirements
This element of the submission package relates to all the customer specific requirements. For bulk
materials, the customer specific requirements shall be recorded on the “Bulk Material Requirements
Checklist”.
Part Submission Warrant
The Part Submission Warrant (PSW) form is a summary of the entire PPAP submission. A PSW is required
for each part number unless otherwise stated by the customer.
5.2.4. PPAP and PSW approval
a) Approved
Approved indicates that the part or material, including all sub-components, meets all customer
requirements. The organization is therefore authorized to ship production quantities of the product.
b) Interim Approval
Interim Approval permits shipment of material for production requirements on a limited time or piece
quantity basis. Interim Approval will only be granted when the organization has submitted a deviation form
that was approved by TAIGA.
c) Rejected
Rejected means that the PPAP submission does not meet customer requirements. In such cases, the
submission and/or process shall be corrected to meet customer requirements. The submission shall be
approved before production parts may be shipped.
5.2.5. New PAPP submission
The Supplier shall submit a notification form to TAIGA for any of the following pending changes:
o Use of different material that was used on the previous approved PPAP
o Any Engineering change
o Production from new or modified tooling
o Location / layout change
o Use of different production or test equipment than the one qualified on the previous approved PPAP
o Change of subcontractor for material, parts or services
Based on the analysis of the notification form, the Supplier shall be asked to submit a revised PPAP for
TAIGA approval PRIOR to beginning of production shipment from the approved changes.
Annual Requalification
To certify the components and raw materials delivered, a dimensional inspection is required each year
following PPAP approval. Under some circumstances, TAIGA could request a resubmission of the full level
3 PPAP package.
SQAM- Rev. 02 | P a g e . 18
6. Process control
6.1. TAIGA Specifications
TAIGA documentation such as Drawings and Engineering Specifications must be reviewed, understood and
agreed upon by the Supplier, prior to launch. It is required that a bubble print is created by the Supplier,
which identifies ALL characteristics, for example, Diameter, Depth, Angle, etc., and are individually
numbered and referenced throughout the process (PFMEA, Control Plan, Work Instructions, Process Plans,
etc.).
6.2. Documentation and Data Control
The Supplier shall control all documents and records relating to the purchase order, including technical
drawings, specifications, engineering changes, work instructions, manufacturing processes, manufacturing
operation sheets, scheduling and quality control plans, as applicable.
6.3. Record Control and Retention
The Supplier shall maintain records of inspections, dispositions, test results and corrective actions to prove
that these operations have been performed for a minimum period of ten (10) years after the part becomes
inactive.
6.4. Pass Through Characteristics (PTC) Requirements
Pass Through Characteristics (PTC) are product characteristics that are created or revealed during the
process and have little to no chance of being detected prior to reaching the customer. Such characteristics
will affect fit, form or function at some point.
Each PTC should be identified in both the PFMEA and Control Plan under the Special
Characteristic/Classification column and identified by the by the [PTC] notation on the drawing. These
characteristics should have a defined inspection method and frequency described in the Control plan. Even
if these PTC characteristics are introduced at a sub-tier supplier level, the tier 1 supplier shall manage the
characteristic (See section 3.1).
6.5. Error and Mistakes Proofing
Whenever possible, TAIGA advocates the implementation of error-proofing methodology during planning
and problem resolution to prevent manufacture of non-conforming products, especially for repetitive
functions, difficult tasks prone to mistakes, or where the cost of error is high.
6.6. Work Instructions
The Supplier shall prepare documented work instructions, as necessary, for all employees having
responsibilities for the operation of processes that impact product quality. These instructions shall be
maintained current and accessible for use at the workstation.
6.7. Control Plan
When APQP or PPAP applies, control plans are required for production phase. Like the FMEA’s, Control
Plans are living documents and are expected to be reviewed and updated as process or product changes.
6.8. Job Set-Up Verification
Verification of product is required any time that a job is set-up, changed over or out of production for a
stated period. The supplier is to verify first piece and in the event of multiple changeovers, last-off
inspection is a recommended practice.
SQAM- Rev. 02 | P a g e . 19
6.9. Control of Monitoring and Measuring Devices
Measuring equipment shall be calibrated and verified (validity of results) at specified intervals, or prior to
use, against measurement standards traceable to international or national measurement standards; when
no such standards exist, the basis for calibration shall be recorded.
6.10. Reworking of Faulty Parts
Reworking faulty parts that are noticed either during our production or as part of a complaint must only be
carried out in agreement with the TAIGA quality management and must be clearly labeled as reworked
parts in each part/bag/box before delivery. This approach should be part of the reaction plan in the control
plan.
6.11. Preventative & Predictive Equipment Maintenance (PM)
To support capacity and quality requirements, it is a necessity that suppliers develop a planned preventive
maintenance system to optimize OEE, process variation and process capability by minimizing unplanned
downtime. As part of the PM program, suppliers should document and review PM actions.
6.12.Product-Related with Embedded Software
Suppliers furnishing product-related software with embedded software shall implement and maintain a
process for software quality assurance of their products.
An assessment process based on ISO 26262 will be utilized to assess supplier’s software development
process. Using prioritization based on risk and potential impact to TAIGA, Suppliers shall retain
documented information of a software development capability self-assessment.
7. Packaging and Labeling
7.1. Handling, storage, and packaging
The supplier shall have a written process in place to ensure that in-process handling, product identification,
storage, preservation, packaging of product including relevant documentation to ensure traceability,
storage of material and delivery will prevent damage, deterioration, contamination, substitution, or misuse
of material.
PACKAGING
Every packaging design shall be approved by TAIGA representative. Suppliers should provide expendable
packaging or returnable containers, where appropriate, that provide sufficient density and protection from
any likely damage that may occur. Expendable materials and packaging must meet local and national
standards for safe disposal and/or recycling. Packaging remains supplier responsibility, regardless of the
approval.
LABELING
Labeling and bar code requirements may vary. The TAIGA representative will provide the Supplier with the
relevant specifications. As a bare minimum, the labelling should include the following information to ensure
traceability: Part number (with revision), Supplier name and Production batch number.
7.2. Identification and traceability of parts, box, shipments
Marking of finished products shall be performed in accordance with the TAIGA instruction.
All boxes must be identified with a label as per TAIGA’s specification: Supplier requirements – box labelling
(SQLF-001 Rev 003).
SQAM- Rev. 02 | P a g e . 20
7.3. Material certification/raw material
When requested by TAIGA, Material certification is compulsory with each shipment and should include the
material test certificate as well as the technical data sheet. The use of substitute material is not permitted
unless authorized by the TAIGA engineering department.
7.4. Tool Marking
All Tools and Gauges, property of TAIGA, must be properly and permanently identified by the Supplier
according to TAIGA requirements. The identification is to contain the following information: Property of
TAIGA, Tool Number, Part Number and Part Name. Suppliers are required to submit significant pictures of
the tooling and update their tooling inventory information at PPAP to receive tooling payment.
8. Quality events (NC, problem solving, recalls)
Continual Improvement
Suppliers should define a process for continual improvement, such as ISO 9004, including Annex B.
8.1. Problem Solving Process
Suppliers should use a reliable close-loop problem-solving method to assess all the nonconformities
communicated by TAIGA. TAIGA does not strictly define which tool to use and when: There may be specific
cases when the TAIGA Quality Representative will require a specific problem-solving tool.
For example (8D Report):
Step Description
1 Team approach Consult and coordinate with relevant stakeholders
2 Describe the Problem State what the problem “Is,” and “Is Not” with respect to what,
where, when, who, how, and how many. Use quantitative terms.
3 Containment Action Immediately contain any suspect product to protect TAIGA and its
customers.
4 Root Cause Verification Identify potential causes, analyze causes for failure mode, validate
root cause(s), and identify solutions.
5 Implement Corrective Implement solution. Document the corrective action: update
Action applicable FMEA, control plan and work instructions.
6 Verify Corrective Action Use check sheets, auditing, sampling, and/or control plans to
monitor process performance for effectiveness and sustained
improvement
7 Prevent Recurrence Implement changes to prevent the same type of error from
occurring in similar products/processes. Update applicable
documents
8 Congratulate the Team Review, approve, and support. Provide resources and team
recognition
Table 7: 8D approach description
SQAM- Rev. 02 | P a g e . 21
8.2. Control of non-conforming products
Shipping of non-conforming materials to TAIGA is not permitted (unless explicitly authorized) and, in any
case, will directly affect the Supplier’s score card rating. Measures shall be taken to ensure the Supplier’s
future product conformance and control. The Supplier is also responsible for their subcontractors’
conformance to requirements.
Containment
When a problem is discovered at the customer facility, the supplier will be notified immediately and all
suspect products must be contained at all locations including, supplier/sub-supplier facilities, warehouses,
parts in transit to the customer or other locations, parts on customer production floor. Suppliers are
expected to have a strong written procedure for containment and control of non-conforming products.
TAIGA reserves the right to charge back all costs associated with supplier caused non-conforming products,
including return of material, loss of production, labor and components, where applicable.
Controlled Quarantine Area
All product which is suspect or non-conforming, for any reason, must be properly identified and stored in a
defined quarantined area, away from the production flow or shipping areas. The Supplier must have a
system and a procedure in place to manage parts in the quarantine area.
Nonconformities
In the event of non-conforming parts, the Supplier will be notified using a Supplier Quality Alert (SQA).
The Supplier complaint shall be related to any issue identified by TAIGA and TAIGA customers, including
quality issues, delivery issues, capacity issues, service issues of mass production parts.
The Supplier’s response requirements for the quality alert are:
• Fast response (Short term containment action) within 24 hrs
• Root cause and actions (Long term action) within 10 days
• Actions implementation and validation within 20 days
The time of implementation could be delayed based on the specific complaint upon TAIGA approval.
Recalls
If TAIGA or any of its customers find or suspect that the products are defective, TAIGA will, to the extent
possible, notify the Supplier. Supplier shall fully cooperate with TAIGA in implementing any recall programs
and/or corrective and preventive action plans. Therefore, the Supplier agrees to reimburse to TAIGA all the
costs associated with the implementation of corrective actions.
9. Deviation Request
A Supplier shall not knowingly ship products that deviate from the technical specifications. If such a
condition exists, the Supplier may ask TAIGA, in writing, to allow shipment of the product under a written
nonconformance deviation.
A Deviation request has a time limit, that shall be indicated in the document, based on number of parts or
period, up to a maximum of 3 (three) months.
If requested by the TAIGA Buyer, the Supplier must send samples of such nonconforming items to TAIGA
for evaluation. The cost of shipping, inspection, and testing required to determine the potential acceptability
of such product will be charged to the Supplier. The Supplier must start working immediately on corrective
actions. In all cases, the Supplier shall fully contain all products suspected of being nonconforming.
SQAM- Rev. 02 | P a g e . 22
A copy of the TAIGA-approved deviation document must be included inside of each box.
10. Supplier Performance and Corrective Actions
10.1. Supplier Quality Performance Evaluation:
Suppliers will be evaluated based on two key indicators.
Quality (% Compliant parts)
This metric defines the Rejected percentage (%). The definition of “rejected parts” is the total number of
parts returned to the Supplier for any valid quality reason (including those caused by shipping and
administrative errors):
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑟𝑒𝑗𝑒𝑐𝑡𝑒𝑑 𝑝𝑎𝑟𝑡𝑠
% Compliant parts = (1 − )𝑥100
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑟𝑒𝑐𝑒𝑖𝑣𝑒𝑑 𝑝𝑎𝑟𝑡𝑠
Based on TAIGA’s expectations, the following table describes the resulting actions or various % reject
values.
% Compliant Category Comment
parts
> 99,9 Meets Meets all the requirements set by TAIGA
expectation
95 – 99,9 Good Satisfactory; no action required
80 - 95 Marginal Systemic corrective action may be required
< 80 Unacceptable Systemic corrective action is required and may require Supplier
to meet with TAIGA management representatives.
Table 8: Requirement for the % of compliant parts
Delivery (OTD)
This metric defines the delivery performance rating using the following formula: On Time Delivery (OTD)
is based on the contract date. The Supplier should systematically inform TAIGA of any delay in delivering
SQAM- Rev. 02 | P a g e . 23
product and provide a new dispatch date. The Supplier is responsible for additional transport costs due to
delays.
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑝𝑎𝑟𝑡𝑠 𝑟𝑒𝑐𝑒𝑖𝑣𝑒𝑑 𝑜𝑛 𝑡𝑖𝑚𝑒
% OTD= 𝑥100
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑝𝑎𝑟𝑡𝑠 𝑟𝑒𝑐𝑒𝑖𝑣𝑒𝑑
% OTD Category Comment
> 98 Meet Meets all the requirements set by TAIGA
expectations
90 - 98 Good Satisfactory; no action required
80 - 89 Marginal Systemic corrective action may be required
< 80 Unacceptable Systemic corrective action is required and may require
Supplier to meet with TAIGA management representatives.
Table 9: Requirement for the % OTD
11. Contact List and Compliance Matrix
Upon receipt and full reading of the contact list and compliance matrix document, the supplier shall fill the
contact list and acknowledge compliance to the various SQAM requirements. In case of non-compliance, the
supplier shall notify TAIGA by filling in the comment / action required column.
12. Management of Hardware and Fasteners
TAIGA has a procedure in place to cover the procurement of hardware and fasteners which are defined as
follow: any item that is used to mechanically join or affix two or more objects together (screws, inserts,
rivets, nuts, bolts, etc.). The Hardware and Fasteners Procedure #01 must be reviewed and signed by any
supplier providing fasteners or hardware of any sort. This procedure is in place to ensure that the products
delivered by the concerned Suppliers are in accordance with what is listed in the TAIGA Standard Hardware
Database.
SQAM- Rev. 02 | P a g e . 24
[READING ORDER TEXT]
SQAM- Rev. 02 | P a g e . 1SQAM- Rev. 02 | P a g e . 2
Contents
1. Introduction...................................................................................................................................................................................3
2. Definitions, Acronyms and Abbreviations.........................................................................................................................4
3. Basic Requirements....................................................................................................................................................................6
4. Supplier Approval Process.......................................................................................................................................................8
5. Product Qualification..............................................................................................................................................................11
6. Process control..........................................................................................................................................................................18
7. Packaging and Labeling..........................................................................................................................................................19
8. Quality events (NC, problem solving, recalls)...............................................................................................................20
9. Deviation Request....................................................................................................................................................................21
10. Supplier Performance and Corrective Actions.............................................................................................................22
11. Contact List and Compliance Matrix.................................................................................................................................23
12. Management of Hardware and Fasteners......................................................................................................................23SQAM- Rev. 02 | P a g e . 3
1. Introduction
1.1. Taiga
Taiga Motors Inc (below “TAIGA”) was founded in 2015 by a group of engineers that believed there
shouldn’texistacompromisebetweenexhilaratingpowersportpursuitandsacrificingtheenvironment.Be
it carving through powder, across lakes or along dirt trails nothing beats instant torque at your fingertips,
silent speed and fresh air.
1.2. Vision
Pioneering Off-Road Electrification
1.3. Mission
Taking on one of the most challenging vehicle segments to electrify, TAIGA has pushed the frontiers of
electrictechnologytoachievetheextremepower,weightandthermalspecificationsrequiredtooutperform
the high performance but polluting 2-stroke engine. The result is the world’s first electric powertrain
designedfromthegroundupthatisfaster,morereliable,moreefficient&betterconnectedtoeveryseason,
and the first line of fully electric recreative vehicles.
1.4. Values
We seek to be a global company, recognized for its competitiveness, excellence, and innovation in off-road
vehicles, all within a framework of the highest standards of integrity. The result is the world’s first electric
snowmobile, designed based on the following values:
- Safety
- Innovation
- Customer Experience Focus
- Trust & Collaboration
- Respect & Responsibility
1.5. Approach
This manual defines the minimum quality requirements for TAIGA Suppliers or TAIGA Partners to ensure
that the product complies with TAIGA customers’ regulatory and safety requirements. These requirements
are set out according to the ISO 9001 standard and TAIGA specific requirements.
1.6. Responsibility of Suppliers
TAIGA recognizes the very important role our Suppliers have in the value we offer our customers. As an
extensionofourownoperations,werelyonourSupplierstoprovidematerial,products,andserviceswhich
meet all the requirements of TAIGA products, applicable specifications, and the quality management
requirements outlined herein.
It is the responsibility of each Supplier to comply with the requirements of this Supplier Quality Assurance
Manual and associated documents referred to throughout the text unless a special agreement is made
between the TAIGA SQA coordinator and the Supplier.SQAM- Rev. 02 | P a g e . 4
2. Definitions, Acronyms and Abbreviations
• The words “shall”, or “must”, indicate a mandatory requirement.
• The word “should” indicates a mandatory requirement with some flexibility allowed in the method
of compliance.
• The term "Supplier" refers to the contractual part of TAIGA’s suppliers and their subcontractors. In
some cases, the Supplier can also be the manufacturer.
Acronyms and abbreviations
ITEM DESCRIPTION
8-D Eight Discipline problem solving
AAR Appearance Approval Report
AIAG Automotive Industry Action Group
APQP Advanced Product Quality Planning
Benchmarking Improvement tool to measure performance or process against other
companies’ best practices
CAD Computer-Aided Design
Containment Immediate short-term Supplier actions
Control Plan Documented description of the process for controlling the product
Corrective Action (CA) Permanent, documented, systemic corrections to the failed processes
Cpk Process Capability Index
FAI First Article Inspection
MSA Measurement System Analysis
OEE Overall Equipment Effectiveness
D/P-FMEA Design/Process Failure Mode and Effect Analysis
Design for
Manufacturability and
Assembly (DFM/DFA)
Simultaneous engineering process designed to optimize the relationship
between design function, manufacturability, and ease of assembly.
Failure Modes and
Effects Analysis
(FMEA)
Systematic activities intended to recognize and evaluate the potential
failure of a product, and the effects and causes of that failure, identify
actions that could eliminate or reduce the chance of the potential failure
occurring, and document the process.
PO Purchase Order
PM Project Management
PPAP Production Part Approval Process
R&R Repeatability and ReproducibilitySQAM- Rev. 02 | P a g e . 5
RPN Risk Priority Number
S/N Serial Number
SPC Statistical Process Control
Table 1: Acronyms and abbreviations
Revision History:
Revision Date Responsible Description of changes
00 2021-10-13 David Maltais First emission
01 2022-09-08 David Maltais Comment added in section 3.3 to take special
machining tolerances into account.
02 2024-02-19 David Maltais Revision of the SQLF has been updated. Section 12
added. Sections 3.2.3 and 3.2.4 requirements
modified. Root cause resolution time increased.SQAM- Rev. 02 | P a g e . 6
3. Basic Requirements
3.1. Critical and Special Requirements
Definition
CriticalCharacteristicsrelatedfeaturesaredesignatedbythepresenceofthesymbol[CC]nexttothefeature
onthedrawingorinaspecification,toindicatethatthefeaturehasthepotentialtoaffectgovernment,safety
andenvironmentalregulationsand/orcanleadtoinjuriestovehicleoperators,passengers,othertravelers,
passers-by or maintenance personnel. If any feature of a part is considered as a critical characteristic, the
part is a critical part.
SpecialCharacteristic relatedfeatures aredesignatedbythepresenceofthesymbol[SC]nexttothefeature
on the drawing or in a specification, to indicate that it has the potential to affect product’s function.
Duetotheseverityofthesedefinedcharacteristics,itisarequirementthattheybeappropriatelystatedand
controlled within the applicable processes.
Related Documentation
Regardingdimensional,material,testandfunctionalrequirementsforproductfeaturesidentifiedasCritical
Characteristic [CC] and Special Characteristic [SC], the following requirements apply and supersede the
general requirements:
o Critical AND Special Characteristics must be clearly identified throughout the manufacturing
process and in all associated documentation such as Process FMEA, Control plans and Work
Instructions
o Capability requirements for parts identified with [CC], [SC] and [PTC] (defined in Section 6.4)
characteristics are described below:
Characteristic Requirement
Critical Characteristic [CC]
Cpk ≥ 1,67 Process under statistical control
or
• Electronic or automated poka-yoke
• Effectiveness verified once per shift
TAIGA approved action plan for achieving
process control and capability
Special Characteristic [SC]
Cpk ≥ 1,33 Process under statistical control
or
• 100% inspection
• TAIGA approved action plan for achieving process
control and capability
Pass Through Characteristics [PTC]
(See section 6.4)
Table 2: CC and SC management
Data records resulting from Statistical Process Control (SPC), automated checking, and inspection results
must be available for download upon request by TAIGA.
Critical and Special
Requirements
Quality
Requirements
Technical
RequirementsSQAM- Rev. 02 | P a g e . 7
3.2. Quality Requirements
3.2.1. Quality Management System Requirements
AllpotentialPrototypeSuppliers arerequiredtohaveastandardQualityManagementSystem basedonthe
minimum requirements of ISO 9001.
All Production Suppliers must have a Quality Management System compliant to ISO 9001 as a minimum,
with the objective of becoming IATF compliant. A copy of the valid certification must be transmitted to
TAIGA by the Supplier.
3.2.2. Conformity to Environmental Regulation
ISO 14001: TAIGA encourages Suppliers to develop a certification plan along the lines of ISO 14001
standard.
3.2.3. IMDS Requirement
SupplierisencouragedtoprovideanIMDSsubmission.Whereappropriate,thesuppliershouldindicatethe
IMDS number in the Part Submission Warrant document. IMDS data must be submitted through
www.mdsystem.com (Ref TAIGA IMDS ID: 234149).
3.2.4. RoHS and REACH
RoHS and REACH compliance is required to sell products in the European Union, China, Korea and some
regions of the United States and Canada. Supplier is required to provide documentation showing
compliance with both RoHS and Reach for all components sourced by TAIGA and intended for production
vehicles. Declarations based on documents such as test reports from third party or regulatory data sheet
are acceptable.
3.3. Technical / Engineering Requirements
Supplier shall comply with all 6 requirements listed below. In the event of a conflict, the more stringent
requirement shall apply. If a conflict related to quality has mutually exclusive requirements, the order of
precedence from highest to lowest will be:
* For the purpose of GD&T, all dimensional information contained in the 3D model is basic and the 2D has
precedence for every feature that is driven by special machining tolerances (e.g., Press fit tolerances).
3.3.1.Technical Drawing, CAD and Geometric Tolerancing
Only products manufactured according to technical drawings approved by TAIGA will be accepted. TAIGA
technical drawings take precedence over any Supplier manufacturing drawings. Also, TAIGA 3D files
override 2D technical drawings specifications. It’s expected that the Supplier has knowledge of Geometric
Dimensioning and Tolerancing (GD&T) as per the ASME Y14.5M-2009 Standard, to provide parts that are
within the tolerances as per TAIGA 2D technical drawings. It’s the Supplier’s responsibility to demonstrate
the part’s compliance to the GD&T tolerancing requirements by using the proper measurement technique
(e.g., Coordinate measurement machine).
GT&C
PO or
Contract
3D Model 2D Print
Supplier
Quality
Manual
Commodity
Specific
AddendumSQAM- Rev. 02 | P a g e . 8
3.3.2. Review of Technical Specifications
The objective of this process is to ensure that the Supplier has a full understanding of the technical
requirements related to the product. The Suppliermust review all the technical documents, standards, and
specifications defining the product and fill the compliance matrix to confirm that each requirement is
understoodandachievable.Intheeventwherearequirementisn’tunderstoodorachievable,anactionplan
needs to be put in place. The compliance matrix shall be sent by TAIGA buyer during the RFQ process.
3.3.3. Design Validation Planning and Reporting (DVP&R)
When applicable (requested by the agreed plan), the Supplier must develop and implement a product test
plan (DVP&R) that must be reviewed and approved by TAIGA Project Representatives. Inputs for the test
planshouldinclude:DFMEA,engineeringspecificationsandanyotherTAIGAdefined/suppliedengineering
requirements.
3.3.4. Design Failure Mode and Effects Analysis – DFMEA
Where applicable, design responsible Suppliers must develop and maintain a DFMEA throughout the life of
the product. DFMEA inputs should include warranty issues, customer concerns, lessons learned, and
address past 8D concerns.
3.3.5. Process Failure Mode and Effects Analysis – PFMEA
A PFMEA is an absolute requirement which must be developed and maintained throughout the life of the
product. PFMEA should also include inputs such as DFMEA, warranty issues, customer concerns, lessons
learned, and past 8D concerns.
4.Supplier Approval Process
Prototype
Supplier
Production
Supplier
Indirect
Supplier
NDA, GTC, SQAM RFQ Closed PO
FAI and PO
Delivery
Prototype
Supplier
active
Prototype Supplier
Active
Prototype
Supplier
Initial
Assessment
Documenta
tion Based
Audit
Visit and On-
Site
Assessment
Production
Supplier
active
RFQ Closed PO PO DeliverySQAM- Rev. 02 | P a g e . 9
TAIGA has defined the following “Supplier Types” for the purpose of classifying its suppliers. It is possible for a single
organizationto qualify as more than one (1) Supplier Type.
TYPE Definition Examples QMS *
Manufacturer
(Production or
Prototype)
A supplier who manufactures:
• a product which is designed by
the supplier or
• a generic product in accordance
with industry standards and
specifications
Catalog Items
Hardware, fasteners
Raw Materials
Chemical products
Software
ISO9001 or
IATF 16949
ISO 26262
(Software)
Subcontractor
(Prototype)
A supplier who manufactures products
or performs special processes in
accordance with TAIGA engineering’s
specifications
TAIGA part#
manufacturer
Build-to-print machine
shop
Processing house
Surface / heat
treatments
Casting / machining
No specific
requiremen
t
Subcontractor
(Production)
ISO9001 or
IATF 16949
Distributor
(Production or
Prototype)
A supplier who purchases and resells
products without processing the
materials internally (apart from re-
packaging, logistics, etc.)
Catalog Items
Hardware, fasteners
Commercial goods
Chemical products
ISO9001
Indirect
Products or
Services
(Indirect)
A supplier providing products, parts
and/or services in support of TAIGA’s
industrial activities but not to be
installed or integrated into TAIGA’s end
products
Contractors
Tools
Consumables
Supplies
No specific
requiremen
t
Laboratory
(Indirect)
A supplier providing laboratory services Calibration
Testing
Analysis
ISO17025
Table 3: Supplier types
* Suppliers are required to implement and maintain a registered Quality Management System (QMS) to
support all applicable elements of the international standard, as defined by the Supplier Type. QMS
certification must be achieved via an accredited Certification/Registration Body (e.g., accredited by ANAB
or another equivalent, nationally recognized accrediting body). Additional ISO14001 certification is
encouraged throughout TAIGA’s Supplier base.
4.1. Supplier Evaluation Process
TAIGA requires all Suppliers to be approved prior to the issuance of contracts. All Suppliers must be
approved by TAIGA Quality, regardless of approvals by customers or other entities.SQAM- Rev. 02 | P a g e . 10
Prototype Supplier:
Suppliers in this family can only supply prototype parts, which are not fully qualified and are not intended
to be used in the final product (production product). A prototype product is an early sample, model, or
release of a product built to test a concept or a process. A prototype is generally used to evaluate a new
design and does not necessarily use the same material or process that will be used for the production part.
Production Supplier
Suppliers in this family can supply prototype AND production parts. They are fully qualified and are
intended to be used for final production products. A production product uses the final material and the
approved process and is approved to be used in the final version of TAIGA products once the formal
qualification process is completed.
Indirect and Service Supplier
IndirectandServiceSuppliers provideTAIGAwithproducts/services notdirectlyrelatedtotheproduction
(forexample:furniture, office products,detergents,facilitymaintenance, manpower,assurance,IT services
etc.).
4.2. Supplier Evaluation Steps
The Supplier Evaluation and Approval Process includes the following steps:
a) Potential Supplier Initial Assessment
TAIGAwillrequesttheSuppliertoprovideacopyofitsqualitymanagementsystemcertificateandcomplete
aPotentialSupplierSelf-Assessment(PSA)ofits business andqualitymanagementsystemandcapabilities,
providing information related to the following criteria:
• Company profile
• Management
• Environment
• Quality
• Logistics
• After market
• Competence
• Product development
• Finance
• Productivity
• Sourcing
b) Documentation Audit
Once the Potential Supplier Self-Assessment (PSA) completed, the assigned Supplier Quality Engineer will
request all the relevant documented evidence related to the criteria part of the PSA. The PSA review and
the audit of the various documents will enable the Supplier Quality Engineer to determine if the Supplier’s
quality management system meets TAIGA requirements.
c) On-Site Assessment
Generally,whenaSupplieris IATF1694/ISOTS16949certifiedbyanaccreditedcertificationbody,TAIGA
will not conduct an on-site assessment of the Supplier’s quality management system against the same
criteria. However, TAIGA, due to product/process complexity or criticality, may elect to conduct on-site
assessments of Supplier products or process capabilities (Process Audit – PA). As a result, findings may be
issued.SQAM- Rev. 02 | P a g e . 11
These assessments could include:
• Quality Management System (QMS)
• Business and Manufacturing Operations
• Continuous Improvement Initiative
• Technology Assessment
• Sub-Tier Supplier Control
4.3. Supplier Status
Based on the Supplier evaluation steps, a Supplier can be classified in one of the below statuses:
Supplier Status description:
• UNDER EVALUATION: The Supplier is under evaluation to verify if it can be part of TAIGA Supplier
panel.
• ACTIVE: The Supplier is fully qualified and is currently a partner of TAIGA in all supply chain activities.
• NBH: New Business Hold – major problems occurred and no clear action plan active to solve them.
• OBSOLETE: The Supplier is obsolete. No business possible until a new evaluation is completed.
Table 4: Supplier status
(*) Active Suppliers can deliver production parts only after part approval in any case
5. Product Qualification
Prototype Part
Production Part
Type Receive RFI/RFQ Proto/sample delivery Production delivery
Under Evaluation yes yes no
Active yes yes yes (*)
New Business Hold no Waiver needed yes
Obsolete no no no
CAD files and Technical
Requirements
FAI
Part Delivery
and QC by
TAIGA
Part is Accepted
CAD Files and
Technical
Requirements
APQP
Process
(When
requested)
Special
Processes
Approval
PPAP
Submission
Part Delivery
and QC by
TAIGA
Part is
AcceptedSQAM- Rev. 02 | P a g e . 12
5.1. Prototype Product Qualification: Documentation Approval
First Article Inspection (FAI)
As a minimum, a First Article Inspection (FAI) is required to initially qualify a prototype part/process for
Supplier approval, unless the PPAP process (below) is used instead. In the event where an IATF certified
supplier produces prototype parts, he shall submit a Level 4 PPAP package.
Furthermore,a new FAImay be requested if thereis an extendedgap of timesince last production.TheFAI
requires that all features and characteristics on the design specification and control plan be inspected and
verified prior to production1. TAIGA FAI form, or other convenient and equivalent document may be used.
5.2. Product Qualification for Production
This section defines the generic requirements for production part qualification and approval. The purpose
is to determine if all TAIGA designand specificationrequirements are properly understood by the Supplier
and that the manufacturing processes have the capability to consistently meet these requirements.
5.2.1. Advanced Product Quality Planning (APQP)
When requested, Supplier shall implement and develop a detailed Advanced Product Quality Plan for the
developmentofprocessesusedtoproduceaspecificpartorfamilyofpart.TheAIAGpublication“Advanced
Product Quality Planning (APQP) and Control Plan” should be used as a reference when developing these
plans.Theseplans shouldalsoincludetheTAIGAspecific requirements presentedinthecurrentdocument.
APQP identifies the tasks to be completed, the expected timing, assigned responsibility for completion and
the critical path.
The objective of the planning process is to deliver the project on time, at the right cost and at the highest
levelofquality.TheinitialdevelopmentoftheAPQPshouldbeginuponreceiptoftheRequestforQuotation
(RFQ). This initial plan should be included as part of the RFQ response package.
The Supplier is responsible for obtaining the latest revision of the applicable AIAG core tool reference
manuals and forms (see Applicable Documents section for where these references may be obtained).
The AIAG Core Tools Manuals are:
• Advanced Product Quality Planning (APQP) and Control Plan
• Production Part Approval Process (PPAP)
• Potential Failure Mode and Effects Analysis (FMEA)
• Measurement Systems Analysis (MSA)
• Statistical Process Control (SPC)
1
ForFirstArticleInspectionguidance,seeAIAGPPAPManual(AppendixC,D,&E)–ProductionPartApproval
Process (available from www.aiag.org).SQAM- Rev. 02 | P a g e . 13
APQP Timing
Suppliers of parts supported by the APQP are required to report the project status at established intervals
during the project development. As a general rule, reviews are held prior to each of the project milestones
or drawing revision releases. Suppliers should prepare for these project review meetings by completing or
updatingtheAPQPreviewtemplate,theirprojectplanandtheprojectmilestonedates.Supplierscanaccess
the APQP review templates on TAIGA website.
APQP Samples
The Supplier shall provide the samples according to the APQP timing plan agreed with TAIGA, and make
sure the samples will meet the quality requirements for each milestone.
The Supplier shall submit the APQP documents (and, eventually, the PPAP) on time as TAIGA required.
TAIGAwillreviewthedocumentsbasedontheISO9001,IATF16949orAIAG.Ifthereisanyissueortiming
delayfortheAPQP documents, TAIGAreleases aSuppliercomplaint according to the risk and requiresroot
cause analysis and improvement report to avoid other occurrences.
5.2.2. Special Processes Documentation approval
For TAIGA, the following processes are managed as special processes as defined in the ISO 9001 standard:
Process
Surface treatment (coating, plating, etc.)
Casting
Metallurgy
Plastics
Electrics and Electronics
Adhesive
Table 5: Special processes in scopeSQAM- Rev. 02 | P a g e . 14
Supplier is responsible to follow the requirements indicated in the purchase order. All first part shipment
must be approved by TAIGA. Shipping approval must be performed as per the following steps:
• Supplier and TAIGA agree on the specific tests and components part of the test plan
• Supplier performs the final inspection on one sample part (destructive test if applicable)
• Supplier must send the test results documents to TAIGA for approval
• TAIGA will analyze the documents and will inform the Supplier if the parts can be shipped
• After the reception of the shipment approval, the Supplier can send the parts
5.2.3. Production Part Approval Process (PPAP)
TheSuppliershallsubmittoTAIGAaProductionPartApprovalProcess (PPAP)level3submissionpackage.
The Supplier is responsible for obtaining the latest revision of the applicable AIAG core tool reference
manuals and forms).
PPAPdefinestheapprovalprocessfornewparts,revisedparts,orpartsproducedfromneworsignificantly
revised production methods. The PPAP process consists of 18 elements that may be required for approval
of production level parts. The PPAP manual contains detailed information, guidelines and sample
documents useful for completing the process requirements. The Production Part Approval Process (PPAP)
demonstrates that the manufacturing process used to produce parts is fully developed, thoroughly tested,
and capable of serial production of parts conforming to the technical specifications.
Every PPAP package must be sent to QUALITY@taigamotors.ca or to the assigned Supplier Quality
representative.
Unless exempted by an approved Waiver from TAIGA, Suppliers may not ship the first batch of production
parts without an approved Part Submission Warrant (PSW) document signed by TAIGA representative.
PPAP Submission Levels
The PPAP submission requirements are normally divided into five classifications or levels, as follows:
• Level 1 – Part Submission Warrant (PSW) only, submitted to TAIGA Quality
• Level 2 – PSW with product samples and limited supporting data
• Level 3 – PSW with product samples and complete supporting data
• Level 4 – PSW and other requirements as defined by the customer
• Level5–PSWwithproductsamplesandcompletesupportingdataavailableforreviewattheSupplier’s
manufacturing locationSQAM- Rev. 02 | P a g e . 15
Table 6: Documents to submit
S – The Supplier will submit documentation and retain copy of records or documentation items at appropriate locations
R – The Supplier shall retain at appropriate locations and make available to TAIGA upon request.
“*” The Supplier shall retain at appropriate location and submit to TAIGA upon request.
Elements of PPAP
Below is the list of all 18 elements accompanied by a brief description for each element:
Design Documentation
Design documentation shall include both customer and the Supplier’s drawings.
Engineering Change Documentation
IfthePPAPis requiredduetoarequestforachangetoapart orproduct,thedocumentationrequesting the
change must be included in the PPAP package. This documentation usually consists of a copy of the
Engineering Change Notice (ECN).
(Customer) Engineering Approval
This documentation usually consists of a copy of the Engineering Change Notice (ECN), approved by the
customer engineering department.
Design Failure Mode and Effects Analysis
Design Failure Mode and Effects Analysis (DFMEA) is a cross-functional activity that examines design risks
by exploring the possible failure modes and their effects on the product or customer and their probability
to occur. The DFMEA is a living document that should be reviewed and updated on a regular basis.
Submission Level
Level
1
Level
2
Level 3
(Default)
Level
4
Level
5
1 Design Record (2D Drawing) R S S * R
2 Engineering Change Documents (if any) such as
ECO/ECP
R S S * R
3 Engineering Approval if required R R S * R
4 DFMEA N/A N/A N/A N/A R
5 Process Flow Diagram R R S * R
6 PFMEA R R S * R
7 Control Plan R R S * R
8 Measurement Systems Analysis (GR&R) R R S * R
9 Dimensional Report R S S * R
10 Material/Performance/Functional Test Results R S S S R
11 Initial Process Studies (Short-term Capability
Study)
R R S * R
12 Qualified Laboratory Documents R R S * R
13 Appearance Approval Inspection Report S S S * R
14 Sample product R S S * R
15 Master Sample R R R * R
16 Checking Aids R R R * R
17 Customer Specific Requirement compliancy R S S S S
18 Parts Submission Warrant (PSW) S S S S SSQAM- Rev. 02 | P a g e . 16
Process Flow Diagram
TheProcessFlowDiagramclearlydescribestheproductionprocessanditssequenceinagraphicalmanner.
Process Failure Mode and Effects Analysis
Process Failure Mode and Effects Analysis (PFMEA) reviews all the steps of the production process to
identify any potential failure of a process and evaluate the risk in terms of severity, occurrence, and
probability to detect failure.
Control Plan
The Control Plan is an output from the PFMEA. The Control Plan lists all product Critical and Special
Characteristics and inspection methods required to deliver products that continually meet the customer
quality requirements.
Measurement System Analysis Studies
Measurement System Analysis (MSA) studies include Gage Repeatability & Reproducibility (R&R) studies
on measurement equipment used during assembly or quality control checks. Calibration records for all
gages and measurement equipment must be included.
Dimensional Results
Each dimension on the drawing is measured on the final assembly to make sure that it falls within
specification.TheresultsarerecordedinaspreadsheetandincludedwithinthePPAPsubmission,atotalof
5units mustbeincludedinthedimensionalreport.Fortooledparts,atotalof5units percavityis required.
Records of Material / Performance Tests
This element should contain a copy of the Design Verification Plan and Report (DVP&R). The DVP&R is a
summary of every validation test performed on the part. It should list each test performed and its result.
This section shall also include material certificate when applicable.
Initial Process Studies
Initial process studies include Statistical Process Control (SPC) charts for the Critical and Special
Characteristics of the product. These studies must demonstrate that the critical processes are stable, have
normal variation and are running near the intended nominal value.
Qualified Laboratory Documentation
Qualified laboratory documentation consists of the industry certifications for any inhouse or outsourced
lab that was involved in completing validation testing.
Appearance Approval Report
TheAppearanceApprovalReport(AAR)isapplicableforcomponentsaffectingappearanceonly.Thisreport
validates that the final product appearance requirements are as per specifications. Requirements include
but are not limited to color, grain, textures, etc.
Sample Production Parts
Sample production parts are sent to the customer for approval and are typically stored at either the
customeror Supplier’s site. A picture of the production part is usually included in the PPAP documentation
along with documentation regarding the part location.
Master Sample
Amastersampleisafinalsampleoftheproductthatisinspectedandsignedoffbythecustomer.Themaster
sample part is used to train operators and serves as a benchmark for comparison to standard production
parts if any quality questions arise.SQAM- Rev. 02 | P a g e . 17
Checking Aids
This is a detailed list of checking aids used by production. It should include all tools used to inspect, test or
measure parts during the assembly process. The list should describe the tool and have its calibration
schedule. Checking aids may include check fixtures, contour, variable and attribute gages, models, or
templates. MSA may be required for all checking aids based on customer requirements.
Customer Specific Requirements
This element of the submission package relates to all the customer specific requirements. For bulk
materials, the customer specific requirements shall be recorded on the “Bulk Material Requirements
Checklist”.
Part Submission Warrant
The Part Submission Warrant (PSW) form is a summary of the entire PPAP submission. A PSW is required
for each part number unless otherwise stated by the customer.
5.2.4. PPAP and PSW approval
a) Approved
Approved indicates that the part or material, including all sub-components, meets all customer
requirements.The organization is therefore authorized to ship production quantities of the product.
b) Interim Approval
Interim Approval permits shipment of material for production requirements on a limited time or piece
quantitybasis.InterimApprovalwillonlybegrantedwhentheorganizationhassubmittedadeviationform
that was approved by TAIGA.
c) Rejected
Rejected means that the PPAP submission does not meet customer requirements. In such cases, the
submission and/or process shall be corrected to meet customer requirements. The submission shall be
approved before production parts may be shipped.
5.2.5. New PAPP submission
The Supplier shall submit a notification form to TAIGA for any of the following pending changes:
o Use of different material that was used on the previous approved PPAP
o Any Engineering change
o Production from new or modified tooling
o Location / layout change
o UseofdifferentproductionortestequipmentthantheonequalifiedonthepreviousapprovedPPAP
o Change of subcontractor for material, parts or services
Based on the analysis of the notification form, the Supplier shall be asked to submit a revised PPAP for
TAIGA approval PRIOR to beginning of production shipment from the approved changes.
Annual Requalification
To certify the components and raw materials delivered, a dimensional inspection is required each year
following PPAP approval. Under some circumstances, TAIGA could request a resubmission of the full level
3 PPAP package.SQAM- Rev. 02 | P a g e . 18
6.Process control
6.1. TAIGA Specifications
TAIGAdocumentationsuchasDrawingsandEngineeringSpecificationsmustbereviewed,understoodand
agreed upon by the Supplier, prior to launch. It is required that a bubble print is created by the Supplier,
which identifies ALL characteristics, for example, Diameter, Depth, Angle, etc., and are individually
numberedand referencedthroughout the process (PFMEA, Control Plan, Work Instructions, Process Plans,
etc.).
6.2. Documentation and Data Control
The Supplier shall control all documents and records relating to the purchase order, including technical
drawings,specifications, engineering changes, work instructions, manufacturing processes, manufacturing
operation sheets, scheduling and quality control plans, as applicable.
6.3. Record Control and Retention
TheSuppliershallmaintainrecordsofinspections, dispositions, testresults andcorrectiveactionstoprove
that these operations have been performed for a minimum period of ten (10) years after the part becomes
inactive.
6.4. Pass Through Characteristics (PTC) Requirements
Pass Through Characteristics (PTC) are product characteristics that are created or revealed during the
process and have little to no chance of being detected prior to reaching the customer. Such characteristics
will affect fit, form or function at some point.
Each PTC should be identified in both the PFMEA and Control Plan under the Special
Characteristic/Classification column and identified by the by the [PTC] notation on the drawing. These
characteristicsshould have a defined inspection method and frequency described in the Control plan. Even
if these PTC characteristics are introduced at a sub-tier supplier level, the tier 1 supplier shall manage the
characteristic (See section 3.1).
6.5. Error and Mistakes Proofing
Whenever possible, TAIGA advocates the implementation of error-proofing methodology during planning
and problem resolution to prevent manufacture of non-conforming products, especially for repetitive
functions, difficult tasks prone to mistakes, or where the cost of error is high.
6.6. Work Instructions
The Supplier shall prepare documented work instructions, as necessary, for all employees having
responsibilities for the operation of processes that impact product quality. These instructions shall be
maintained current and accessible for use at the workstation.
6.7. Control Plan
When APQP or PPAP applies, control plans are required for production phase. Like the FMEA’s, Control
Plans are living documents and are expected to be reviewed and updated as process or product changes.
6.8. Job Set-Up Verification
Verification of product is required any time that a job is set-up, changed over or out of production for a
stated period. The supplier is to verify first piece and in the event of multiple changeovers, last-off
inspection is a recommended practice.SQAM- Rev. 02 | P a g e . 19
6.9. Control of Monitoring and Measuring Devices
Measuring equipment shall be calibrated and verified (validity of results) at specified intervals, or prior to
use, against measurement standards traceable to international or national measurement standards; when
no such standards exist, the basis for calibration shall be recorded.
6.10. Reworking of Faulty Parts
Reworking faulty parts that are noticedeither during our productionor as part of acomplaintmust onlybe
carried out in agreement with the TAIGA quality management and must be clearly labeled as reworked
partsineachpart/bag/box beforedelivery.This approachshouldbepartofthereactionplaninthecontrol
plan.
6.11. Preventative & Predictive Equipment Maintenance (PM)
To support capacity and quality requirements, it is a necessity that suppliers develop a planned preventive
maintenance system to optimize OEE, process variation and process capability by minimizing unplanned
downtime. As part of the PM program, suppliers should document and review PM actions.
6.12.Product-Related with Embedded Software
Suppliers furnishing product-related software with embedded software shall implement and maintain a
process for software quality assurance of their products.
An assessment process based on ISO 26262 will be utilized to assess supplier’s software development
process. Using prioritization based on risk and potential impact to TAIGA, Suppliers shall retain
documented information of a software development capability self-assessment.
7.Packaging and Labeling
7.1. Handling, storage, and packaging
Thesuppliershallhaveawrittenprocessinplacetoensurethatin-processhandling,productidentification,
storage, preservation, packaging of product including relevant documentation to ensure traceability,
storageofmaterialand delivery will prevent damage, deterioration, contamination,substitution,ormisuse
of material.
PACKAGING
Every packaging design shall be approved by TAIGA representative. Suppliers should provide expendable
packagingorreturnablecontainers, whereappropriate,thatprovidesufficientdensityandprotectionfrom
any likely damage that may occur. Expendable materials and packaging must meet local and national
standards for safe disposal and/or recycling. Packaging remains supplier responsibility, regardless of the
approval.
LABELING
Labelingandbarcoderequirementsmayvary.TheTAIGArepresentativewillprovidetheSupplierwiththe
relevantspecifications.Asabareminimum,thelabellingshouldincludethefollowinginformationtoensure
traceability: Part number (with revision), Supplier name and Production batch number.
7.2. Identification and traceability of parts, box, shipments
Marking of finished products shall be performed in accordance with the TAIGA instruction.
Allboxes mustbeidentifiedwithalabelas perTAIGA’s specification:Supplierrequirements –box labelling
(SQLF-001 Rev 003).SQAM- Rev. 02 | P a g e . 20
7.3. Material certification/raw material
When requested by TAIGA, Material certification is compulsory with each shipment and should includethe
material test certificate as well as the technical data sheet. The use of substitute material is not permitted
unless authorized by the TAIGA engineering department.
7.4. Tool Marking
All Tools and Gauges, property of TAIGA, must be properly and permanently identified by the Supplier
according to TAIGA requirements. The identification is to contain the following information: Property of
TAIGA, Tool Number, Part Number and Part Name. Suppliers are required to submit significant pictures of
the tooling and update their tooling inventory information at PPAP to receive tooling payment.
8.Quality events (NC, problem solving, recalls)
Continual Improvement
Suppliers should define a process for continual improvement, such as ISO 9004, including Annex B.
8.1. Problem Solving Process
Suppliers should use a reliable close-loop problem-solving method to assess all the nonconformities
communicatedby TAIGA. TAIGA does not strictly define which tool to use and when: There may be specific
cases when the TAIGA Quality Representative will require a specific problem-solving tool.
For example (8D Report):
Step Description
1 Team approach Consult and coordinate with relevant stakeholders
2 Describe the Problem State what the problem “Is,” and “Is Not” with respect to what,
where, when, who, how, and how many. Use quantitative terms.
3 Containment Action Immediately contain any suspect product to protect TAIGA and its
customers.
4 Root Cause Verification Identify potential causes, analyze causes for failure mode, validate
root cause(s), and identify solutions.
5 Implement Corrective
Action
Implement solution. Document the corrective action: update
applicable FMEA, control plan and work instructions.
6 Verify Corrective Action Use check sheets, auditing, sampling, and/or control plans to
monitor process performance for effectiveness and sustained
improvement
7 Prevent Recurrence Implement changes to prevent the same type of error from
occurring in similar products/processes. Update applicable
documents
8 Congratulate the Team Review, approve, and support. Provide resources and team
recognition
Table 7: 8D approach descriptionSQAM- Rev. 02 | P a g e . 21
8.2. Control of non-conforming products
Shipping of non-conforming materials to TAIGA is not permitted (unless explicitly authorized) and, in any
case, will directly affect the Supplier’s score card rating. Measures shall be taken to ensure the Supplier’s
future product conformance and control. The Supplier is also responsible for their subcontractors’
conformance to requirements.
Containment
When a problem is discovered at the customer facility, the supplier will be notified immediately and all
suspectproducts must be contained at all locations including, supplier/sub-supplier facilities, warehouses,
parts in transit to the customer or other locations, parts on customer production floor. Suppliers are
expected to have a strong written procedure for containment and control of non-conforming products.
TAIGAreservestherighttochargebackallcostsassociatedwithsuppliercausednon-conformingproducts,
including return of material, loss of production, labor and components, where applicable.
Controlled Quarantine Area
All product whichis suspect or non-conforming, foranyreason,must be properly identified and storedina
defined quarantined area, away from the production flow or shipping areas. The Supplier must have a
system and a procedure in place to manage parts in the quarantine area.
Nonconformities
In the event of non-conforming parts, the Supplier will be notified using a Supplier Quality Alert (SQA).
The Supplier complaint shall be related to any issue identified by TAIGA and TAIGA customers, including
quality issues, delivery issues, capacity issues, service issues of mass production parts.
The Supplier’s response requirements for the quality alert are:
• Fast response (Short term containment action) within 24 hrs
• Root cause and actions (Long term action) within 10 days
• Actions implementation and validation within 20 days
The time of implementation could be delayed based on the specific complaint upon TAIGA approval.
Recalls
If TAIGA or any of its customers find or suspect that the products are defective, TAIGA will, to the extent
possible,notifytheSupplier.SuppliershallfullycooperatewithTAIGAinimplementinganyrecallprograms
and/orcorrectiveandpreventive actionplans.Therefore, theSupplieragreestoreimburse toTAIGAallthe
costs associated with the implementation of corrective actions.
9.Deviation Request
A Supplier shall not knowingly ship products that deviate from the technical specifications. If such a
condition exists, the Supplier may ask TAIGA, in writing, to allow shipment of the product under a written
nonconformancedeviation.
A Deviation request has a time limit, that shall be indicated in the document, based on number of parts or
period, up to a maximum of 3 (three) months.
If requested by the TAIGA Buyer, the Supplier must send samples of such nonconforming items to TAIGA
forevaluation.Thecostofshipping,inspection,andtestingrequiredtodeterminethepotentialacceptability
ofsuchproductwillbecharged totheSupplier. TheSuppliermuststartworking immediatelyoncorrective
actions. In all cases, the Supplier shall fully contain all products suspected of being nonconforming.SQAM- Rev. 02 | P a g e . 22
A copy of the TAIGA-approved deviation document must be included inside of each box.
10. Supplier Performance and Corrective Actions
10.1. Supplier Quality Performance Evaluation:
Suppliers will be evaluated based on two key indicators.
Quality (% Compliant parts)
This metric defines the Rejected percentage (%). The definition of “rejected parts” is the total number of
parts returned to the Supplier for any valid quality reason (including those caused by shipping and
administrative errors):
% Compliant parts = (1 −
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑟𝑒𝑗𝑒𝑐𝑡𝑒𝑑 𝑝𝑎𝑟𝑡𝑠
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑟𝑒𝑐𝑒𝑖𝑣𝑒𝑑 𝑝𝑎𝑟𝑡𝑠
)𝑥100
Based on TAIGA’s expectations, the following table describes the resulting actions or various % reject
values.
% Compliant
parts
Category Comment
> 99,9 Meets
expectation
Meets all the requirements set by TAIGA
95 – 99,9 Good Satisfactory; no action required
80 - 95 Marginal Systemic corrective action may be required
< 80 Unacceptable Systemic corrective action is required and may require Supplier
to meet with TAIGA management representatives.
Table 8: Requirement for the % of compliant parts
Delivery (OTD)
This metric defines the delivery performance rating using the following formula: On Time Delivery (OTD)
is based on the contract date. The Supplier should systematically inform TAIGA of any delay in deliveringSQAM- Rev. 02 | P a g e . 23
product and provide a new dispatch date. The Supplier is responsible for additional transport costs due to
delays.
% OTD=
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑝𝑎𝑟𝑡𝑠 𝑟𝑒𝑐𝑒𝑖𝑣𝑒𝑑 𝑜𝑛 𝑡𝑖𝑚𝑒
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑝𝑎𝑟𝑡𝑠 𝑟𝑒𝑐𝑒𝑖𝑣𝑒𝑑
𝑥100
% OTD Category Comment
> 98 Meet
expectations
Meets all the requirements set by TAIGA
90 - 98 Good Satisfactory; no action required
80 - 89 Marginal Systemic corrective action may be required
< 80 Unacceptable Systemic corrective action is required and may require
Supplier to meet with TAIGA management representatives.
Table 9: Requirement for the % OTD
11.Contact List and Compliance Matrix
Upon receipt and full reading of the contact list and compliance matrix document, the supplier shall fill the
contactlistandacknowledgecompliancetothevariousSQAMrequirements.Incase ofnon-compliance,the
supplier shall notify TAIGA by filling in the comment / action required column.
12. Management of Hardware and Fasteners
TAIGA has a procedure in place to cover the procurement of hardware and fasteners which are defined as
follow: any item that is used to mechanically join or affix two or more objects together (screws, inserts,
rivets, nuts, bolts, etc.). The Hardware and Fasteners Procedure #01 must be reviewed and signed by any
supplier providing fastenersor hardwareofany sort. This procedureis inplace toensure that the products
deliveredbytheconcernedSuppliersareinaccordancewithwhatislistedintheTAIGAStandardHardware