Ref. Ares(2024)5558133 - 31/07/2024
Retrofitting of fishing fleets with low payback time
and easy to deploy solutions for footprint and GHG emissions reduction
PROJECT MANAGEMENT PLAN
Deliverable number D8.1
WP8, T8.3
KU
“This project has received funding from the European Union’s Horizon Europe Research and Innovation Programme under Grant Agreement No. 101157663. Views and opinions expressed
are however those of the author(s) only and do not necessarily reflect those of the European Union or the European Climate, Infrastructure and Environment Executive Agency (CINEA).
Neither the European Union nor the granting authority can be held responsible for them”
DOCUMENT NUMBER: D8.1
DOCUMENT TITLE: PROJECT MANAGEMENT PLAN
DUE DELIVERY DATE: 31/07/24
LEAD PARTNER: KU
PROJECT TITLE: Retrofitting of fishing fleets with low payback time and easy to deploy so-
lutions for footprint and GHG emissions reduction
PROJECT ACRONYM: REFEST
CALL IDENTIFIER: HORIZON-MISS-2023-OCEAN-01
TOPIC: HORIZON-MISS-2023-OCEAN-01-04
GRANT AGREEMENT: 101157663
DELIVERABLE TYPE
R Document, report X
DMP Data Management Plan
DEM Demonstrator, pilot, prototype
O Other
DISSEMINATION LEVEL
PU Public (fully open) X
SEN Sensitive, limited under the conditions of the Gran Agreement
Proprietary rights statement
This document contains information proprietary to the REFEST consortium. Neither this document,
nor the information contained herein, shall be used, duplicated or communicated by any means to any
third party, in whole or in parts, except prior written consent of the REFEST consortium.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 2
DISCLAIMER OF WARRANTIES
This document has been prepared by REFEST project partners as an account of work carried
out within the framework of the GA contract Nº 101157663.
Neither Project Coordinator, nor any signatory party of REFEST Project Consortium Agree-
ment, nor any person acting on behalf of any of them:
• makes any warranty or representation whatsoever, express or implied,
• with respect to the use of any information, apparatus, method, process, or similar
item disclosed in this document, including merchantability and fitness for a par-
ticular purpose, or
• that such use does not infringe on or interfere with privately owned rights, includ-
ing any party's intellectual property, or
• that this document is suitable to any user’s circumstance; or
• assumes responsibility for any damages or other liability whatsoever (including
any consequential damages, even if Project Coordinator or any representative of a
signatory party of the REFEST Project Consortium Agreement has been advised of
the possibility of such damages) resulting from your selection or use of this docu-
ment or any information, apparatus, method, process, or similar item disclosed in
this document.
Funded by the European Union. Views and opinions expressed are however those of the au-
thor(s) only and do not necessarily reflect those of the European Union or the CINEA.
The European Union cannot be held responsible for them.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 3
HISTORY OF CHANGES
Version Partner name Date Comments
V1 KU 1st Draft 25/07/2024
VALIDATION
Authors Reviewers
KU TSC
ABBREVIATIONS | ACRONYMS
Acronym Description
CA Consortium Agreement
D Deliverable
DoA Description of Action
GA Grant Agreement
GHG Greenhouse gas
PC Project Coordinator
PO Project Officer
REA European Research Executive Agency
ToC Table of Content
WP Work package
TSC Technical & Steering Committee
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 4
Table of Content
EXECUTIVE SUMMARY ................................................................ 7
1. INTRODUCTION ..................................................................... 8
2. PROJECT INFORMATION ...................................................... 10
2.1 PROJECT COORDINATOR .............................................................. 12
2.2 GENERAL ASSEMBLY .................................................................... 13
2.3 TECHNICAL & STEERING COMMITTEE ............................................ 14
2.4 EXECUTIVE BOARD ....................................................................... 15
2.5 INNOVATION COMMITTEE ........................................................... 15
2.6 WORK PACKAGE LEADER .............................................................. 16
2.7 TASK LEADER ............................................................................... 16
3. COMMUNICATION PROCEDURES ......................................... 17
3.1 CONTACTS LIST ............................................................................ 17
3.2 PROJECT REPOSITORY .................................................................. 17
3.3 MEETINGS ................................................................................... 18
4. DECISION MAKING PROCEDURES ......................................... 20
5. QUALITY CONTROL .............................................................. 21
5.1 QUALITY CONTROL OF THE DELIVERABLES..................................... 21
5.2 PROJECT MONITORING AND REPORTING ...................................... 22
5.3 POTENTIAL DELAYS AND CORRECTIVE ACTIONS ............................. 23
6. RISKS MANAGEMENT .......................................................... 24
7. CONCLUSIONS ..................................................................... 25
8. DEVIATIONS ........................................................................ 26
ANNEX 1 – DELIVERABLE TEMPLATE .......................................... 27
ANNEX 2 – POWER POINT TEMPLATE ........................................ 28
ANNEX 3 - DELIVERABLES REVIEW MATRIX................................ 29
ANNEX 4 – RISK MANAGEMENT REGISTER ................................ 33
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 5
List of Figures
Figure 1: REFEST Organisational structure ............................................................................................ 12
List of Tables
Table 1: REFEST consortium role and sector......................................................................................... 11
Table 2: WPs leaders .......................................................................................................................................... 16
Table 3: Time and notice of the meetings ................................................................................................ 18
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 6
EXECUTIVE SUMMARY
D8.1 Project Management Plan is conceived as a single point of reference to REFEST consor-
tium in the day-by-day project activities, facilitating the management and revision of
REFEST workflow. It includes an internal guide with the main procedures and rules on pro-
ject management, including Work Package Leader, contacts, financial data, project KPIs, tem-
plates and guidelines.
D8.1 does not replace neither the Grant Agreement nor the Consortium Agreement, rather
D8.1 complements both GA and CA and must be used in conjunction with these two docu-
ments.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 7
1. INTRODUCTION
REFEST project, funded by the European Commission, with GA reference 101157663 aims
to achieve TRL6 – procedures and technologies to secure the reduction of fuel consumption
and GHG emissions up to 40% reduction compared to the original design. The solutions pro-
posed will be designed to ready to deploy in a broad range of small fishing vessels and they
are characterized by a low CAPEX and OPEX requirements to significantly reduce the pay-
back time (to 5-6 years). Ensuring upscaling of the proposed solutions after project imple-
mentation till 2030.
REFEST consortium is composed by 14 partners across 10 different countries (Lithuania,
Spain, Sweden, Denmark, Italy, France, Poland, Germany, Norway & Turkey). REFEST project
has integrated in its consortium large and small companies with a large experience in this
field to cover all the value chain. 4 research and technology organisations (KU, AIMPLAS,
RISE, MIR), 2 large industries (RINA-C, ELKON), 7 SMEs (NHX, BLUENAV, EAS, CALSENS,
ENCO, TUCO, GEMI) and fishmen association (LFPA) are part of the consortium with the aim
to ensure successful project implementation, impact, take-up, and exploitation of results.
The main innovations are summarized as follow:
- Innovative design by the use bulbs and spray rails that allow to improve hull hydro-
dynamics, to minimize the water friction and reduce external and underwater noise.
- Recyclable acrylic resins reinforced with carbon/glass fibres for manufacture of hull
appendages and use thermoplastic composites to produce battery housing.
- Integration of air lubrication systems for small vessels.
- Propulsion systems based on RIM drive solutions and its hybridization with current
diesel engines.
- Integration of multi-functional optical fibre sensors for fishing ships monitoring.
- Cloud-based Eco-driving software with AI will be integrated as well as a class 1 Dy-
namic Positioning System (DPS) based on the RIM-drive propulsion.
- Safe, cost efficient and light Li Ion battery system for long cycle life in cold operation
environments.
- Battery system with a high percentage of reusable and recyclable parts.
- Optimized Lithium Battery pack, EMS, and PMS to maximize the energy consumption
in the vessel.
- Low-weight (< 20 g/Wp) and flexible photovoltaic panels (FPV) based on silicon cells
and flexible connector to be integrate in ship. Including walkable version to increase
the available surface for FPV installation.
- Three retrofit demo traditional fishing ships in North Sea (Denmark & Norway) and
Baltic Sea (Lithuania).
Additionally, REFEST aims to ensure that presented solutions and technologies are suitable,
acceptable, and economically viable for the end-users by including fishing communities, re-
searchers, etc. but also, they have not a negative effect over the north and Baltic Sea envi-
ronment by application of analytical and modelling methods for impact assessment on ma-
rine environment and biodiversity.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 8
Main REFEST’s impacts to fulfil the REFEST solutions, aligned with the Mission: Restore our
Ocean, seas, & waters by 2030 are aiming to contribute to the following points:
- The project will propose and validate the hybridisation of fishing ships to achieve a signif-
icant electrification of them by integrate flexible solar panels and batteries that feed to an
auxiliary RIM engine and the electrical needs of the ship (illumination, air conditioning and
control).
- REFEST will plan to reduce the consumption of fuel up to 40% by the integration of seven
main solutions (hull appendages, air-lubrication, RIM engines, batteries, flexible PV panels,
full power management system and eco-driving solutions), the result will be a reduction of
thousands of kt per month in the fishing sector.
- The project aims to reduce the production of harmful pollution by the use solvent-free pro-
cesses, water, and air lubrication systems. REFEST will not pose any significant harm to the
six environmental objectives that are set out in EU Taxonomy Regulation and Art 17 of Reg-
ulation (EU) No 2020/852.
- REFEST will also contribute to the connectivity and digitalization of the ships to improve
their efficiency, security and reduce fuel consumption. Two main approaches will be consid-
ered – 1) use of EMS/PMS not limited to safety issues and optimisation of consumption of
electricity in the ship by accurate manage of them, but also extended to storage data to be
used in predictive maintenance and to have data for future improvements in the Electrical
Architecture of the retrofit ships. 2) use of AI tools to develop an eco-driving software that
allows using the electrical or diesel engine, when each one will be more suitable, reducing
fuel and energy consumption and maximising shipping autonomy. They will also connect to
COPERNCUS data or other data sources to have the capacity to take the right decision on-
time.
- The REFEST proposed activity does not accomplish with specific data measurements at sea
relevant to EMODnet database or EMODNet operations.
- The underwater shipborne noise along with the noise directivity will be measured within
the REFEST framework of retrofitted (as though before retrofitting) small fishery vessels,
providing the data of spectral properties of the vessels underwater noise. The noise meas-
urements results will serve in support of development of fishery vessels source spectral
models and evaluation of source levels as well in the assessment of underwater noise effects
on marine fauna. The gathered underwater noise measurement data (audio files) will be
made available through the REFEST web source dissemination channels. The research meth-
odology, results and other outcomes of underwater research will be summarized in the tech-
nical report, that will be made available publicly.
This document works as a guide that shows the partners’ roles in different phases of the
project. In the sections below the general specifications and the working structure of the
project is shown, including the team compositions and capabilities, specific objectives and
expectations, work plans and schedules, checkpoints for controlling work progress and in-
teractions with other work packages are detailed for each work package (WP).
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 9
2. PROJECT INFORMATION
The overall methodological approach in 36 months REFEST project will be based on 5 dis-
tinct PILLARS and implemented in 8 WPs: PILLAR 1 – Specifications of retrofitting require-
ments; PILLAR 2 – Material Development and Technology Evaluation; PILLAR 3 – Retrofit
the selected fishing vessels; PILLAR 4 – Impact Assessment; PILLAR 5 – Engagement and
Market Update.
Partner Acronym Type Role Country
Coordinator
WP8 leader.
RTO
KU Naval studies, emis- Lithuania
sions and underwater
noise assessment
Support for the
definition and
implementation of
AIMPLAS RTO REFEST. Thermo- Spain
plastic composites
(battery box & hulls
appendages). Sen-
sor’s integration
Support for the
definition and
RISE RTO implementation of Sweden
REFEST. Naval stud-
ies, Air Lubrication
WP1 leader
Biodiversity & ma-
MIR RTO rine impact assess- Poland
ment, stakeholders’
involvement.
Support for the
definition and
implementation of
NXH SME France
REFEST. Lightweight
and flexible photovol-
taic panels.
BLUENAV SME WP4 leader France
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 10
RIM engine optimiza-
tion and Eco-driving
technologies
Support for the
definition and
EAS SME implementation of Germany
REFEST, Lithium Ion-
Batteries
WP2 leader
CALSENS SME Fibre-optic multi sen- Spain
sors
WP6 leader
RINA-C IND LCA, LCC, s-LCA, reg- Italy
ulatory gap assess-
ment
WP3 leader
Electric network re-
ELKON IND configuration, electri- Turkey
cal power manage-
ment, digitalization.
Support for the
definition and
ENCO SME implementation of Italy
REFEST, Business
plan, exploitation and
IPR.
WP5 leader
TUCO SME Denmark
Demo boat provider
WP7 leader
LFPA ASSOCIATION Lithuania
Demo boat provider
Support for the
definition and
GEMI SME implementation of Norway
REFEST, Demo boat
provider
Table 1: REFEST consortium role and sector
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 11
REFEST ORGANISATIONAL STRUCTURE
REFEST organisational structure comprises the following Consortium Bodies:
- The Coordinator, the legal entity acting as the intermediary between the Parties and
the Granting Authority.
- The General Assembly as the decision-making body of the consortium. The Technical
& Steering Committee consisting of the Coordinator and the Work Package Leaders.
- The Executive Board supports the Coordinator in the preparation of the biannual
consortium meetings, establishing the critical points to be addressed with a complete
overview of the project.
- The Innovation Committee manages the innovation process, overseeing stakeholder
engagement to facilitate innovation and impact. Additionally, the committee focuses
on communication, dissemination, and building innovation capacity within the pro-
ject.
- The Work Package leaders and Task leaders responsible for the overall management
and coordination at WP and Task level and the achievement of the defined results.
Figure 1: REFEST Organizational structure
Section 6 of the Consortium Agreement defines the details of REFEST Governance Structure,
the next paragraphs present relevant information for the development of the foreseen activ-
ities.
2.1 PROJECT COORDINATOR
KU, Coordinator of REFEST Project, shall be the intermediary between the Parties and the
Granting Authority and shall perform all tasks assigned to it as described in the Grant Agree-
ment and in the Consortium Agreement.
KU is in charge of the overall administrative management of the project, being the single
point of contact with the European Commission (EC). KU is responsible for the execution of
the administrative and financial activities of the GA; it is also in charge of ensuring effective
communication, collaboration and cooperation within the Consortium by defining docu-
ment, reporting and control procedures.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 12
The Coordinator shall be responsible for:
• Monitoring compliance by the Parties with their obligations.
• Keeping the address list of Members and other contact persons updated and availa-
ble.
• Collecting, reviewing to verify consistency, and submitting reports, other delivera-
bles (including financial statements and related certifications) and specific requested
documents to the Granting Authority.
• Preparing the meetings, proposing decisions and preparing the agenda of the General
Assembly meetings, chairing the meetings, preparing the minutes of the meetings,
and monitoring the implementation of decisions taken at meetings.
• Transmitting promptly documents and information connected with the Project to
any other Parties concerned.
• Administering the financial contribution of the Granting Authority and fulfilling the
financial tasks described in Section 7.2 of the Consortium Agreement.
• Providing, upon request, the Parties with official copies or originals of documents
that are in the sole possession of the coordinator when such copies or originals are
necessary for the Parties to present claims.
• If one or more of the Parties are late in submission of any project deliverable, the
Coordinator may nevertheless submit the other Parties’ Action deliverables and all
other documents required by the Grant Agreement to the Funding Authority in time.
• The Coordinator shall not enlarge its role beyond the tasks specified in this Consor-
tium Agreement and in the Grant Agreement.
• The Coordinator shall not be entitled to act or to make legally binding declarations
on behalf of any other Party or of the Consortium.
Responsible partner: KU
2.2 GENERAL ASSEMBLY
The General Assembly consists of one representative of each Party (Member).
Each Member shall be deemed to be duly authorised to deliberate, negotiate and decide on
all matters listed in Section 6.3.7 of this Consortium Agreement and summarized below:
The General Assembly, shall be free to act on its own initiative to formulate proposals and
take decisions in accordance with the procedures set out herein.
The Coordinator shall chair all meetings of the General Assembly, unless decided otherwise
by the General Assembly.
The Parties agree to abide by all decisions of the General Assembly.
This does not prevent the Parties from exercising their veto rights, according to Section
6.3.5, or from submitting a dispute for resolution in accordance with the provisions of set-
tlement of disputes in Section 11.8 of this Consortium Agreement.
The following decisions shall be taken by the General Assembly:
Content, finances and intellectual property rights.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 13
- Proposals for changes to Annexes 1 and 2 of the Grant Agreement to be agreed by the
Granting Authority.
- Changes to the Consortium Plan.
- Modifications or withdrawal of Background in Attachment 1 (Background Included)
- Additions to Attachment 3 (List of Third Parties for simplified transfer according to
Section 8.3.2) of the CA.
- Additions to Attachment 4 (Identified entities under the same control) of the CA.
Evolution of the consortium.
- Entry of a new Party to the Project and approval of the settlement on the conditions
of the accession of such a new Party.
- Withdrawal of a Party from the Project and the approval of the settlement on the
conditions of the withdrawal.
- Proposal to the Granting Authority for a change of the Coordinator.
- Proposal to the Granting Authority for suspension of all or part of the Project.
- Proposal to the Granting Authority for termination of the Project and the Consortium
Agreement.
Breach, defaulting party status and litigation.
- Identification of a breach by a Party of its obligations under this Consortium Agree-
ment or the Grant Agreement.
- Declaration of a Party to be a Defaulting Party.
- Remedies to be performed by a Defaulting Party.
- Termination of a Defaulting Party’s participation in the consortium and measures re-
lating thereto.
- Steps to be taken for litigation purposes and the coverage of litigation costs in case of
joint claims of the parties of the consortium against a Party (Article 7.1.4 of the CA).
In the case of abolished tasks as a result of a decision of the General Assembly, Members
shall rearrange the tasks of the Parties concerned. Such a rearrangement shall take into con-
sideration any prior legitimate commitments which cannot be cancelled.
Responsible partner: KU
Members: one per partner
Frequency of the meetings: at least twice per year
2.3 TECHNICAL & STEERING COMMITTEE
The Technical Steering Committee (TSC) is composed of one member from each partner or-
ganization and plays a crucial role in overseeing the technical progress and quality of the
project. Its primary responsibility is to review deliverables, ensuring they meet the stand-
ards and requirements, following the methodology detailed in Section 5.
Through regular assessments and feedback, the committee maintains the project's technical
integrity and drives its successful execution.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 14
Responsible partner: RISE
Members: one per WP leader
Frequency of the meetings: At least quarterly
2.4 EXECUTIVE BOARD
The Executive Board (EB) plays a crucial role in the strategic management of the project,
ensuring alignment with overall objectives and timelines. Led by AIMPLAS, the EB supports
the coordinator in preparing the consortium meetings, which are held twice a year. One-two
months before each consortium meeting, the EB convenes to conduct an overview of the
project, identifying critical points for the next six months. During these meetings, they re-
view the Grant Agreement to ensure that all necessary aspects are clearly understood and
can be completed on time.
Additionally, the EB helps identify the most relevant issues to be discussed at the in-person
meetings, ensuring they are effective and focused on the project’s key objectives. This pro-
active approach not only addresses challenges effectively but also drives the overall success
of the project.
Responsible partner: AIMPLAS
Members: KU, CALSENS, TUCO, LFPA
Frequency of the meetings: at least twice per year
2.5 INNOVATION COMMITTEE
The Innovation Committee plays a pivotal role in managing the innovation process within
the project, ensuring that it progresses smoothly and effectively. This involves overseeing
stakeholder engagement, which is crucial for fostering collaboration and leveraging diverse
perspectives to facilitate innovation and maximize impact.
In addition to managing these engagements, the Innovation Committee places a strong em-
phasis on communication and dissemination. It ensures that innovative outcomes and
knowledge are effectively shared both within the project team and with external audiences,
promoting transparency and encouraging the adoption of project results.
Responsible partner: ENCO
Members: LFPA
Frequency of the meetings: at least twice per year
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 15
2.6 WORK PACKAGE LEADER
Each Work Package has a designated Work Package Leader responsible for:
- Coordinating his/her Work Packages tasks with and among the Parties and potential
third parties participating in those tasks.
- Ensuring the quality control of the said Parties contributions.
- Gathering these contributions to prepare the corresponding high-quality Work Pack-
age deliverables and milestones.
- Dealing with all issues concerning the provision of high-level services as described in
Annex I of the Grant Agreement.
- Monitoring all Project activities in order to have regularly an up-to-date idea of state
of progress of the Project, the performance of the concerned Parties and potential
third parties responsible for the activities of the Work Package.
- Where appropriate, suggest the Technical and Steering Committee changes and ad-
justments to the original Work Plan and/or Consortium Plan at any time deemed nec-
essary.
- If deemed necessary, handle any disagreement that may arise among the Parties in-
volved in their Work Package(s) regarding the implementation of the Project.
- Being responsible for reporting on Work Packages led to the Commission, including
requesting partner inputs as necessary.
WP number WP Partner
WP1 MIR
WP2 CALSENS
WP3 ELKON
WP4 BLUENAV
WP5 TUCO
WP6 RINA-C
WP7 LFPA
WP8 KU
Table 2: WPs leaders
2.7 TASK LEADER
Task leaders are responsible for the execution and overall coordination of the tasks assigned
to them in the implementation plan. Furthermore, each Task Leader is responsible for the
coordination of the partners involved in the task and quality control of the activities carried
out by the said partner.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 16
3. COMMUNICATION PROCEDURES
REFEST consortium is using a set of tools to ensure the proper communication and manage-
ment of the project. An online workspace has been created using TEAMS/SHAREPOINT, ac-
cessible through the project website and through TEAMS/SHAREPOINT account using this
link: link. All the members of the consortium received the invitation to join the team.
3.1 CONTACTS LIST
An excel file has been shared among the partners to collect all name, surname, emails of the
team and also their involvement in the different WPs in order to smoothly send different
emails to the right person. Through the excel file, partners can select persons involved in the
different WPs/activities and contact them. The list is organized as reported below:
- General Assembly
- Technical & Steering Committee
- Executive Board
- Innovation Committee
- WP7
The contact list is continuously updated by each partner, any modification to the access on
TEAMS/SHAREPOINT is notified to the Project Coordinator (PC), in charge of adding/re-
moving new persons.
To ensure all the emails are processed by each partner, when an email is sent the reference
“REFEST” must be included before any other text in the subject line. The PC should be in-
cluded in any email regarding the progress of the project.
For any external communication, the PC is the contact point with the funding authority – the
European Research Executive Agency (REA) and he will take regular contact with the Project
Officer by email, the Funding & Tender Portal and using any other communication means
(e.g. telephone).
3.2 PROJECT REPOSITORY
REFEST TEAMS/SHAREPOINT folder is associated to the SharePoint, the repository is man-
aged by PC and ENCO.
Different folders have been created to manage and collect all the documents per type and
category. Below the list of existing folders:
- Administrative documents
- Deliverables submitted
- Events
- General
- Meetings
- Periodic Reports
- Risk Management Register
- Synergies
- Templates
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 17
- WP1
- WP2
- WP3
- WP4
- WP5
- WP6
- WP7
- WP8
- …
The private TEAMS/SHAREPOINT folder is also used for online meetings and short and im-
mediate communications through the chat.
TEAMS/SHAREPOINT also ensures the quality control of all the activities considering this
tool includes the recording of the meetings and the attendance register.
3.3 MEETINGS
Regular meetings are planned to monitor the project progresses, review the achievements,
discuss on technical aspects, and solve any potential issue it may occur during the project
execution.
Any Member:
- Should be present or represented at any meeting;
- May appoint a substitute or a proxy to attend and vote at any meeting;
- And shall participate in a cooperative manner in the meetings.
Article 6.3.2 of the CA defines time and notice of each meeting, the table is also reported
below:
Ordinary meeting Extraordinary Meeting
General Assembly At least twice a year At any time upon request of the Steering
Committee or 1/3 of the Members of the
General Assembly
45 calendar days 15 calendar days
Executive Board At least twice a year
At any time upon request of any Member
1-2 months before Gen- of the Steering Committee
eral Assembly
Technical & Steering At any time upon request of any Member
At least quarterly
Committee of the Steering Committee
Innovation committee At least twice a year At any time upon request of any Member
of the Innovation Committee
Table 3: Time and notice of the meetings
In addition to the meetings listed below, WPs and tasks leaders can plan and organize meet-
ings as many times as needed during the project in presence or via TEAMS/SHAREPOINT.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 18
All the materials: agenda, attendance list, minutes, registration of the meetings will be up-
loaded on TEAMS/SHAREPOINT in order to inform all the partners.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 19
4. DECISION MAKING PROCEDURES
Any decision is taken following a 5-step process:
1. Identification of the topic/decision: once a decision must be taken, the partner in-
volved identify the decision and tentative alternatives.
2. Communication to the project coordinator and the decision-making partners.
3. Analysis of the decision, after having analysed alternatives and impacts.
4. Take action.
5. Review the decision taken and its real impacts.
Meetings and decision procedures, voting rules and quorum, veto rights to be followed as
descried in CA Section 6.
Settlement of disputes among the parties are defined in CA Article 11.8
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 20
5. QUALITY CONTROL
In this section both the quality check of the deliverables and the quality control of the activ-
ities to be developed during the project lifetime and are explained to ensure that all the ex-
pected outcomes are met as well as the consistency of the project outputs.
5.1 QUALITY CONTROL OF THE DELIVERABLES
Deliverables are the results of the activities carried out during the project execution, includ-
ing REFEST’s results and progress. Type and Dissemination level are defined in the DoA,
however they shall be understandable for non-technical people, easy to read and complete;
including as many information as possible related to the activities carried out, results
achieved and impacts.
Each deliverable must include the following elements:
- Cover page
- Quality checklist
- Document details
- Disclaimer of warranties
- History of changes, authors, and reviewers
- Table of content
- Executive summary
- List of abbreviations and acronyms
- Introduction
- Conclusions
- Deviations
- Annex (if any)
The content of each deliverable varies according to the activities carried out per task.
A Deliverable Template has been uploaded on TEAMS/SHAREPOINT and is included as An-
nex 1 of this document.
The language used is always British English.
To ensure a good quality and uniformity of each deliverable, a review process has been de-
fined, including timing and responsible partner in charge of the review.
- 45 days before the official submission deadline: the lead beneficiary responsible for
the deliverable must circulate the ToC.
- 30 days before the official submission, the lead beneficiary responsible for the deliv-
erable must send the consolidated version (v0.1) of the deliverable to the WP leader.
- 21 days before the official submission, the WP leader sends his/her comments to the
lead beneficiary responsible for the deliverable.
- 14 days before the official submission, the lead beneficiary responsible for the deliv-
erable send the consolidated version (v0.2) of the deliverable to the reviewer.
- 7 days before the official submission, the reviewer sends his/her comment to the lead
beneficiary responsible for the deliverable.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 21
- 3 days before the official submission, the lead beneficiary responsible for the deliv-
erable sends the final version (v0.3) to the PC for the last revision.
- Before the deadline is reached, the PC submits the deliverable through the Funding
& tender Portal.
The timeline, responsible partners and reviewers have been included in the Annex 3 of this
deliverable: REVIEW MATRIX. The Matrix is also available on TEAMS/SHAREPOINT.
To facilitate the exchanges of files and information among partners, a dedicated folder has
been created on TEAMS/SHAREPOINT – WP folder - DELIVERABLES. The partner in charge
of the deliverables, the WP leader and the reviewers will upload each version of the deliver-
able in this folder, also to give the opportunity to the other partners to read and comment
the deliverable if needed.
The final submitted version of each deliverable will be uploaded to the repository on
TEAMS/SHAREPOINT.
All public deliverables will be uploaded on the project website and on TEAMS/SHAREPOINT
in directory “Deliverables submitted”.
During the review process it is mandatory to use track changes.
The following criteria must be met per each deliverable:
1. Relevance & Accuracy: always include the respective references, to use a language
and a structure in line with the target audience. Use of the defined template to ensure
uniform appearance.
2. Completeness: include reliable, real and complete information; clearly explaining the
work done and results achieved.
3. Added value: to include relevant information, that will create a value and potential
impacts for the readers.
4. Clarity: to avoid any spelling errors and to not disclose any sensitive information.
5. Language: use of British English.
6. Timing: respect the internal and official deadlines.
7. Disclaimer: always include references to the EU funds.
5.2 PROJECT MONITORING AND REPORTING
Two levels of monitoring and reporting will be followed by REFEST consortium to ensure
the project will successfully deliver all the outcomes and expected results.
The first level is at internal way, done by the PC with the support of each WP leader to con-
stantly review all the progress made by the consortium in carrying out the activities. An in-
ternal review is foreseen at M10, linked with the release of the second tranche of the first
pre-financing.
The second level is the official one foreseen in REFEST GA with the REA (PO and external
reviewers). External reviewers to be involved in the review will be experts specialized in the
topic of the project and will be proposed by the PO.
All due considered, three types of reporting are required:
1. Internal Interim Report at M10.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 22
2. Continuous reporting, through deliverables submission, milestones, risks monitoring,
publications, results, dissemination and communication activities, standards, IPR, da-
tasets, impacts, other results.
3. Periodic reports at M18 and M36
M10 internal interim report will ensure the project is progressing well in terms of deadlines,
activities and results. The information collected will be also used to complete the Periodic
Report.
Two official reporting periods have been defined in the GA. The first reporting report will be
submitted not later than 60 days after the end of the reporting period 1 corresponding to
M1 – M18. The 2nd reporting period correspond to the end of the project - M36. The official
report will be submitted 60 days after the end of the reporting period 2 corresponding to
M19 - M36.
The periodic reports consist of:
- Technical Part contribution
- Status of WP
- Project Summary for Publications
Per each reporting period a financial statement is also required, containing lump sum con-
tributions as indicated in the Annex 2 of the GA, for the WPs that were completed during the
reporting period. For the last reporting period, the beneficiaries may exceptionally also de-
clare partial lump sum contributions for WPs that were not completed (e.g. due to force
majeure or technical impossibility). Lump sum contributions which are not declared in a
financial statement will not be taken into account by the granting authority.
5.3 POTENTIAL DELAYS AND CORRECTIVE ACTIONS
If any potential delay will occur, the responsible partner must inform the PC in due time
explaining the reason of the delays and corrective actions.
Any potential risks, deviations, corrective actions must be reported to the PC who will be in
charge of solving potential issues also by informing the PO.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 23
6. RISKS MANAGEMENT
A planned and controlled approach to the risks management is an imperative and indispen-
sable step to ensure the correct execution and delivery of the project results and expected
outcomes.
Risks may affect in a positive or negative way the project and it is really important to define
a strategy and contingency plan to avoid potential negative effects.
This section summarizes REFEST Risk Management Plan to constantly monitor potential
risks and the effects they could have on the project.
A list of risks has been defined during the proposal writing stage, it has been revised and
implemented during the GAP phase and included in the DoA. A continuous monitoring of the
risks will be done during the project execution, revising and updating them if needed.
A Risk Management Register has been implemented and updated on TEAMS/SHAREPOINT,
it has been also included as Annex 4 to this deliverable. The final aim of the register is to
record and monitor all possible risks and any subsequent actions required. On the base of
the Risk Management Register the Risk identification report will be prepared with the due
date of M9.
Per each identified risk, a mitigation measure has been provided including the likelihood
and severity of each risk.
In the first version of the Risk Management Register the degree of criticality and the proba-
bility of risk happening have been included, assigning per each risk a grade. During the pro-
ject execution and risks monitoring the success of intervention will be monitored.
WP leaders are responsible for monitoring the risks related to their WP, every partner must
notify any potential risk to the respective WP leader in order to define potential contingency
plan to mitigate the risk.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 24
7. CONCLUSIONS
Deliverable 8.1 contains REFEST Project Management Plan. This report aims to act as a guid-
ance for the 14 consortium partners of REFEST to understand the project structure, imple-
mentation phases and procedures.
The final aim of this Deliverable is to give a management structure to the entire consortium,
with activities, deadlines, and templates to be followed and used when preparing the official
reports.
Each WP leader, partner, or team, will further develop their methods and strategies to ex-
change information and facilitate the interaction of activities, always using this document as
a baseline.
As mentioned above, D8.1 complements the Grant Agreement and Consortium Agreement
of REFEST and should be used in conjunction with these two documents.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 25
8. DEVIATIONS
This deliverable has been provided according to timeline with no major deviations.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 26
ANNEX 1 – DELIVERABLE TEMPLATE
The Deliverable template is available on TEAMS/SHAREPOINT at the following link.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 27
ANNEX 2 – POWER POINT TEMPLATE
The PowerPoint template is available on TEAMS/SHAREPOINT at the following link.
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page 28
ANNEX 3 - DELIVERABLES REVIEW MATRIX
Del. Re-
Deliverable Diss.
lated Deliverable Name WP Leader Type Due Date Review Date Reviewer
No Level
No
Requirements for materials, compo-
D1.1 D1 WP1 KU R PU 31 Jan 2025 24 Jan 2025 TSC
nents, and demo-ships
Report of impact assessment of marine
D1.2 D2 WP1 MIR R PU 30 Apr 2026 23 Apr 2026 TSC
environment
Report of impact assessment of Baltic &
D1.3 D3 WP1 MIR R PU 31 Mar 2027 24 Mar 2027 TSC
North Sea biodiversity
Designs of hull appendages for the
D2.1 D4 WP2 KU R SEN 31 Oct 2025 24 Oct 2025 TSC
demo-ships
Standardization and modularization of
D2.2 D5 WP2 KU R PU 31 Jan 2026 24 Jan 2026 TSC
the appendage designs
Report of thermoplastic composites for
D2.3 D6 WP2 AIMPLAS R PU 31 Oct 2025 24 Oct 2025 TSC
hull appendages
Report of manufacture of fibre-optic
D2.4 D7 WP2 CALSENS DEM SEN 31 Oct 2025 24 Oct 2025 TSC
multi-sensors
Report of integration of fibre-optic sen-
D2.5 D8 WP2 AIMPLAS DEM PU 31 Jan 2026 24 Jan 2026 TSC
sors in composites
Report of ship energy efficiency on elec-
D3.1 D9 WP3 ELKON R SEN 31 Oct 2025 24 Oct 2025 TSC
trical architecture
“This project has received funding from the European Union’s Horizon Europe Research and Innovation Programme under Grant Agreement No. 101157663. Views and opinions expressed
are however those of the author(s) only and do not necessarily reflect those of the European Union or the European Climate, Infrastructure and Environment Executive Agency (CINEA).
Neither the European Union nor the granting authority can be held responsible for them”
Del. Re-
Deliverable Diss.
lated Deliverable Name WP Leader Type Due Date Review Date Reviewer
No Level
No
Report of data driven PMS & EMS devel-
D3.2 D10 WP3 ELKON R PU 31 Jan 2026 24 Jan 2026 TSC
opment
Report on battery cell selection and elec-
D3.3 D11 WP3 EAS R PU 31 Jan 2025 24 Jan 2025 TSC
trical model
Summary report of cell characterization
D3.4 D12 WP3 EAS R PU 31 Jul 2025 24 Jul 2025 TSC
and BMS parameters
Report on mechanical design for batter-
D3.5 D13 WP3 KU R PU 31 Oct 2025 24 Oct 2025 TSC
ies for cold weathers
Report of composites from thermoplas-
D3.6 D14 tics and synthetic fibres for battery box. WP3 AIMPLAS R PU 31 Oct 2025 24 Oct 2025 TSC
Materials datasheet.
Modification of flexible PV panels for
D3.7 D15 WP3 NXH DEM PU 31 Jan 2026 24 Jan 2026 TSC
their integration in ships
D4.1 D16 Report of eco-driving solutions WP4 BLUENAV R PU 31 Oct 2025 24 Oct 2025 TSC
Report of RIM engine power increase
D4.2 D17 WP4 BLUENAV DEM PU 31 Jan 2026 24 Jan 2026 TSC
and localization
Report of Air lubrication system meth-
D4.3 D18 WP4 RISE R PU 31 Oct 2025 24 Oct 2025 TSC
ods and designs
Report of Air lubrication system compo-
D4.4 D19 WP4 RISE R SEN 31 Jan 2026 24 Jan 2026 TSC
nent design
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page
30
Del. Re-
Deliverable Diss.
lated Deliverable Name WP Leader Type Due Date Review Date Reviewer
No Level
No
Standardization & modularization of the
D4.5 D20 WP4 RISE R PU 31 Oct 2025 24 Oct 2025 TSC
air-lubrication designs
Update of Standardization & modulariza-
D4.6 D42 WP4 RISE R PU 31 Mar 2027 24 Mar 2027 TSC
tion of the air-lubrication designs
Report of scale-up the production of re-
D5.1 D21 quired materials and parts for the target WP5 TUCO R PU 31 Oct 2026 24 Oct 2026 TSC
retrofitting solutions.
Report of scale-up the manufacture aux-
D5.2 D22 WP5 NXH R PU 31 Oct 2026 24 Oct 2026 TSC
iliar retrofitting solutions
Retrofitting solutions implemented in
D5.3 D23 WP5 TUCO R PU 31 Oct 2026 24 Oct 2026 TSC
each ship
Demonstrators: three ships with new
D5.4 D24 WP5 TUCO DEM PU 30 Apr 2027 23 Apr 2027 TSC
retrofitting solutions
Report of main drawbacks detected and
D5.5 D25 the improvement proposals in the short WP5 LFPA R PU 30 Apr 2027 23 Apr 2027 TSC
and medium term
Holistic decommissioning, and recycling
D5.6 D26 WP5 AIMPLAS R PU 31 Mar 2027 24 Mar 2027 TSC
study of components
D6.1 D27 Report of LCA/LCC assessment WP6 RINA-C R PU 31 Jan 2027 24 Jan 2027 TSC
D6.2 D28 Report of SLCA assessment WP6 RINA-C R PU 31 Jan 2027 24 Jan 2027 TSC
D6.3 D29 Report on H&S assessment WP6 RINA-C R PU 31 Jan 2027 24 Jan 2027 TSC
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page
31
Del. Re-
Deliverable Diss.
lated Deliverable Name WP Leader Type Due Date Review Date Reviewer
No Level
No
Report on toxicological and safety as-
D6.4 D30 WP6 AIMPLAS R PU 31 Mar 2027 24 Mar 2027 TSC
pects
D6.5 D31 Regulatory gap assessment report WP6 RINA-C R PU 31 Mar 2027 24 Mar 2027 TSC
Communication Toolkit, Public website
D7.1 D32 WP7 ENCO R PU 31 Jul 2024 26 Jul 2024 TSC
& Social Media groups
D7.2 D33 Update of Policy recommendations WP7 RINA-C R PU 28 Feb 2027 21 Feb 2027 TSC
Plan for Dissemination, Exploitation,
D7.3 D34 WP7 ENCO R PU 31 Oct 2024 24 Oct 2024 TSC
Communication PDEC
D7.4 D35 Business Model and Business Plan WP7 ENCO R SEN 31 Oct 2025 24 Oct 2025 TSC
D7.5 D36 Policy recommendations WP7 RINA-C R PU 31 Oct 2025 24 Oct 2025 TSC
D7.6 D37 Data Management Plan WP7 ENCO DMP PU 31 Oct 2024 24 Oct 2024 TSC
D7.7 D40 Clustering activities report WP7 ENCO R PU 31 Mar 2027 24 Mar 2027 TSC
Data Management Plan – updated ver-
D7.8 D41 WP7 ENCO DMP PU 31 Oct 2025 24 Oct 2025 TSC
sion
D7.9 D43 Data Management plan final version WP7 ENCO DMP PU 31 Mar 2027 24 Mar 2027 TSC
Update of Business Model and Business
D7.10 D44 WP7 ENCO R SEN 31 Mar 2027 24 Mar 2027 TSC
Plan
D8.1 D38 Project Management Plan WP8 KU R PU 31 Jul 2024 26 Jul 2024 TSC
D8.2 D39 Risk identification – KU in– public report WP8 KU R PU 31 Jan 2025 24 Jan 2025 TSC
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page
32
ANNEX 4 – RISK MANAGEMENT REGISTER
Risk Degree of critical- Probability of Estimated Feasibility / Conclusion
Proposed Mitigation
Description WP ity of the risk risk happening Success of Intervention
number Measures
(1 low- 10 high) (1 low - 10 high) (1 low- 10 high)
All Rights Reserved. REFEST Project. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page
33
[READING ORDER TEXT]
“This project has receivedfunding from the European Union’s Horizon EuropeResearch and Innovation ProgrammeunderGrant AgreementNo.101157663. Views and opinions expressed
are however those of the author(s) only and do not necessarily reflect those of the European Union or the European Climate, Infrastructure and Environment Executive Agency (CINEA).
Neither the European Union nor the granting authority can be held responsiblefor them”
Retrofitting of fishing fleets with low payback time
and easy to deploysolutions for footprint and GHG emissions reduction
PROJECT MANAGEMENT PLAN
Deliverable number D8.1
WP8, T8.3
KU
Ref. Ares(2024)5558133 - 31/07/2024All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page2
DOCUMENT NUMBER: D8.1
DOCUMENT TITLE: PROJECT MANAGEMENT PLAN
DUE DELIVERY DATE:31/07/24
LEAD PARTNER: KU
PROJECT TITLE: Retrofitting of fishing fleets with low payback time and easy to deploy so-
lutions for footprint and GHG emissions reduction
PROJECT ACRONYM: REFEST
CALL IDENTIFIER: HORIZON-MISS-2023-OCEAN-01
TOPIC: HORIZON-MISS-2023-OCEAN-01-04
GRANT AGREEMENT: 101157663
DELIVERABLE TYPE
R Document, report X
DMP Data Management Plan
DEM Demonstrator, pilot, prototype
O Other
DISSEMINATION LEVEL
PU Public (fully open) X
SEN Sensitive, limited under the conditions of the Gran Agreement
Proprietary rights statement
This document contains information proprietary to the REFESTconsortium.Neither this document,
nor the information contained herein, shall be used, duplicated or communicated byany means to any
third party, in whole or in parts,except prior writtenconsent of the REFESTconsortium.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page3
DISCLAIMER OF WARRANTIES
ThisdocumenthasbeenpreparedbyREFESTprojectpartnersasanaccountofworkcarried
out within the framework of the GA contract Nº 101157663.
Neither Project Coordinator, nor any signatory party of REFEST Project Consortium Agree-
ment, nor any person acting on behalf of any ofthem:
• makes any warranty or representation whatsoever, express or implied,
• with respect to the use of any information, apparatus, method, process, or similar
item disclosed in this document, including merchantability and fitness for a par-
ticular purpose, or
• that such usedoes not infringeonor interferewith privatelyowned rights,includ-
ing any party's intellectual property, or
• that this document is suitable to any user’s circumstance; or
• assumes responsibility for any damages or other liability whatsoever (including
anyconsequential damages,even if Project Coordinator or anyrepresentativeofa
signatorypartyoftheREFEST Project Consortium Agreement has been advised of
the possibility of such damages) resulting from your selection or use of this docu-
ment or any information, apparatus, method, process, or similar item disclosed in
this document.
Funded by the European Union.Views and opinions expressed arehowever those ofthe au-
thor(s) only and do not necessarily reflect those of the European Union or the CINEA.
The European Union cannot be held responsible for them.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page4
HISTORY OF CHANGES
Version Partner name Date Comments
V1 KU 1st Draft 25/07/2024
VALIDATION
Authors Reviewers
KU TSC
ABBREVIATIONS | ACRONYMS
Acronym Description
CA Consortium Agreement
D Deliverable
DoA Description of Action
GA Grant Agreement
GHG Greenhouse gas
PC Project Coordinator
PO Project Officer
REA European Research Executive Agency
ToC Table of Content
WP Work package
TSC Technical & Steering CommitteeAll RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page5
Table of Content
EXECUTIVE SUMMARY................................................................ 7
1. INTRODUCTION..................................................................... 8
2. PROJECT INFORMATION...................................................... 10
2.1 PROJECTCOORDINATOR..............................................................12
2.2 GENERALASSEMBLY....................................................................13
2.3 TECHNICAL&STEERINGCOMMITTEE............................................14
2.4 EXECUTIVEBOARD.......................................................................15
2.5 INNOVATIONCOMMITTEE...........................................................15
2.6 WORKPACKAGELEADER..............................................................16
2.7 TASKLEADER...............................................................................16
3. COMMUNICATION PROCEDURES......................................... 17
3.1 CONTACTSLIST............................................................................17
3.2 PROJECTREPOSITORY..................................................................17
3.3 MEETINGS...................................................................................18
4. DECISION MAKING PROCEDURES......................................... 20
5. QUALITY CONTROL.............................................................. 21
5.1 QUALITYCONTROLOFTHEDELIVERABLES.....................................21
5.2 PROJECTMONITORINGANDREPORTING......................................22
5.3 POTENTIALDELAYSANDCORRECTIVEACTIONS.............................23
6. RISKS MANAGEMENT .......................................................... 24
7. CONCLUSIONS..................................................................... 25
8. DEVIATIONS ........................................................................ 26
ANNEX 1 – DELIVERABLE TEMPLATE.......................................... 27
ANNEX 2 – POWER POINT TEMPLATE........................................ 28
ANNEX 3 - DELIVERABLES REVIEW MATRIX................................ 29
ANNEX 4 – RISK MANAGEMENT REGISTER ................................ 33All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page6
List of Figures
Figure 1: REFEST Organisational structure............................................................................................12
List of Tables
Table 1: REFEST consortium role and sector.........................................................................................11
Table 2: WPs leaders..........................................................................................................................................16
Table 3: Time and notice of the meetings................................................................................................18All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page7
EXECUTIVE SUMMARY
D8.1 Project Management Plan is conceived as a singlepoint ofreferenceto REFEST consor-
tium in the day-by-day project activities, facilitating the management and revision of
REFEST workflow. It includes an internal guidewith the main procedures and rules on pro-
jectmanagement,includingWorkPackageLeader,contacts,financialdata,projectKPIs,tem-
plates and guidelines.
D8.1 does not replace neither the Grant Agreement nor the Consortium Agreement, rather
D8.1 complements both GA and CA and must be used in conjunction with these two docu-
ments.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page8
1.INTRODUCTION
REFEST project, funded by the European Commission, with GA reference 101157663 aims
to achieve TRL6 – procedures and technologies to secure the reduction of fuel consumption
and GHG emissions upto40% reductioncompared to theoriginaldesign.Thesolutionspro-
posed will be designed to ready to deploy in a broad range of small fishing vessels and they
are characterized by a low CAPEX and OPEX requirements to significantly reduce the pay-
back time (to 5-6 years). Ensuring upscaling of the proposed solutions after project imple-
mentation till 2030.
REFEST consortium is composed by 14 partners across 10 different countries (Lithuania,
Spain,Sweden,Denmark,Italy,France,Poland,Germany,Norway&Turkey).REFESTproject
has integrated in its consortium large and small companies with a large experience in this
field to cover all the value chain. 4 research and technology organisations (KU, AIMPLAS,
RISE, MIR), 2 large industries (RINA-C, ELKON), 7 SMEs (NHX, BLUENAV, EAS, CALSENS,
ENCO,TUCO,GEMI)and fishmen association(LFPA)arepart oftheconsortium with theaim
to ensuresuccessful project implementation, impact, take-up, and exploitation of results.
The main innovations are summarized as follow:
- Innovative design by the use bulbs and spray rails that allow to improve hull hydro-
dynamics, to minimize the water friction and reduce external and underwater noise.
- Recyclable acrylic resins reinforced with carbon/glass fibres for manufacture of hull
appendages and use thermoplastic composites to produce battery housing.
- Integration of air lubrication systems for small vessels.
- Propulsion systems based on RIM drive solutions and its hybridization with current
diesel engines.
- Integration of multi-functional optical fibre sensors for fishing ships monitoring.
- Cloud-based Eco-driving software with AI will be integrated as well as a class 1 Dy-
namic Positioning System (DPS) based on the RIM-drive propulsion.
- Safe, cost efficient and light Li Ion battery system for long cycle life in cold operation
environments.
- Battery system with a high percentage of reusable and recyclable parts.
- Optimized LithiumBatterypack,EMS,and PMSto maximizetheenergyconsumption
in the vessel.
- Low-weight(<20g/Wp)andflexiblephotovoltaicpanels(FPV)basedonsiliconcells
and flexible connector to be integrate in ship. Including walkable version to increase
the available surface for FPV installation.
- Three retrofit demo traditional fishing ships in North Sea (Denmark & Norway) and
Baltic Sea (Lithuania).
Additionally,REFEST aims to ensurethat presented solutions and technologies aresuitable,
acceptable, and economically viable for the end-users by including fishing communities, re-
searchers, etc. but also, they have not a negative effect over the north and Baltic Sea envi-
ronment by application of analytical and modelling methods for impact assessment on ma-
rine environment and biodiversity.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page9
Main REFEST’s impacts to fulfil theREFEST solutions,aligned with theMission:Restoreour
Ocean, seas, & waters by 2030 are aiming to contribute to the following points:
- The project will propose and validate the hybridisation of fishing ships to achieve a signif-
icant electrification of them by integrate flexible solar panels and batteries that feed to an
auxiliary RIM engine and the electrical needs of the ship (illumination, air conditioning and
control).
- REFEST will plan to reduce the consumption of fuel up to 40% by the integration of seven
main solutions (hull appendages, air-lubrication, RIM engines, batteries, flexible PV panels,
full power management system and eco-driving solutions), the result will be a reduction of
thousands of kt per month in the fishing sector.
- Theproject aims to reducetheproduction ofharmfulpollution bytheusesolvent-freepro-
cesses, water, and air lubrication systems. REFEST will not pose any significant harm to the
six environmental objectives that are set out in EU Taxonomy Regulation and Art 17 of Reg-
ulation (EU) No 2020/852.
- REFEST will also contribute to the connectivity and digitalization of the ships to improve
their efficiency,securityand reducefuel consumption.Twomain approaches will beconsid-
ered – 1) use of EMS/PMS not limited to safety issues and optimisation of consumption of
electricity in the ship by accurate manage of them, but also extended to storage data to be
used in predictive maintenance and to have data for future improvements in the Electrical
Architecture of the retrofit ships. 2) use of AI tools to develop an eco-driving software that
allows using the electrical or diesel engine, when each one will be more suitable, reducing
fuel and energy consumption and maximising shipping autonomy. They will also connect to
COPERNCUS data or other data sources to have the capacity to take the right decision on-
time.
-TheREFESTproposedactivitydoesnotaccomplishwithspecificdatameasurementsatsea
relevant to EMODnet database or EMODNet operations.
- The underwater shipborne noise along with the noise directivity will be measured within
the REFEST framework of retrofitted (as though before retrofitting) small fishery vessels,
providing the data of spectral properties of the vessels underwater noise. The noise meas-
urements results will serve in support of development of fishery vessels source spectral
models and evaluation ofsourcelevels aswellintheassessment ofunderwaternoiseeffects
on marine fauna. The gathered underwater noise measurement data (audio files) will be
madeavailablethroughtheREFESTwebsourcedisseminationchannels.Theresearchmeth-
odology,resultsandotheroutcomesofunderwaterresearchwillbesummarizedinthetech-
nical report, that will be made available publicly.
This document works as a guide that shows the partners’ roles in different phases of the
project. In the sections below the general specifications and the working structure of the
project is shown, including the team compositions and capabilities, specific objectives and
expectations, work plans and schedules, checkpoints for controlling work progress and in-
teractions with other work packages are detailed for each work package (WP).All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page10
2. PROJECT INFORMATION
The overall methodological approach in 36 months REFEST project will be based on 5 dis-
tinct PILLARS and implemented in 8 WPs: PILLAR 1 – Specifications of retrofitting require-
ments; PILLAR 2 – Material Development and Technology Evaluation; PILLAR 3 – Retrofit
the selected fishing vessels; PILLAR 4 – Impact Assessment; PILLAR 5 – Engagement and
Market Update.
Partner Acronym Type Role Country
KU RTO
Coordinator
WP8 leader.
Naval studies, emis-
sionsandunderwater
noise assessment
Lithuania
AIMPLAS RTO
Support for the
definition and
implementation of
REFEST. Thermo-
plastic composites
(battery box & hulls
appendages). Sen-
sor’s integration
Spain
RISE RTO
Support for the
definition and
implementation of
REFEST. Naval stud-
ies, Air Lubrication
Sweden
MIR RTO
WP1 leader
Biodiversity & ma-
rine impact assess-
ment, stakeholders’
involvement.
Poland
NXH SME
Support for the
definition and
implementation of
REFEST. Lightweight
andflexiblephotovol-
taic panels.
France
BLUENAV SME WP4 leader FranceAll RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page11
RIM engine optimiza-
tion and Eco-driving
technologies
EAS SME
Support for the
definition and
implementation of
REFEST, Lithium Ion-
Batteries
Germany
CALSENS SME
WP2 leader
Fibre-opticmulti sen-
sors
Spain
RINA-C IND
WP6 leader
LCA, LCC, s-LCA, reg-
ulatory gap assess-
ment
Italy
ELKON IND
WP3 leader
Electric network re-
configuration, electri-
cal power manage-
ment, digitalization.
Turkey
ENCO SME
Support for the
definition and
implementation of
REFEST, Business
plan, exploitation and
IPR.
Italy
TUCO SME
WP5 leader
Demo boat provider
Denmark
LFPA ASSOCIATION
WP7 leader
Demo boat provider
Lithuania
GEMI SME
Support for the
definition and
implementation of
REFEST, Demo boat
provider
Norway
Table 1: REFEST consortium role and sectorAll RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page12
REFEST ORGANISATIONAL STRUCTURE
REFEST organisational structure comprises the following Consortium Bodies:
- The Coordinator, the legal entity acting as the intermediary between the Parties and
the Granting Authority.
- TheGeneral Assemblyas thedecision-making bodyoftheconsortium.TheTechnical
& Steering Committee consisting of the Coordinator and the Work Package Leaders.
- The Executive Board supports the Coordinator in the preparation of the biannual
consortiummeetings,establishingthecriticalpointstobeaddressedwithacomplete
overview of the project.
- The Innovation Committee manages the innovation process, overseeing stakeholder
engagement to facilitate innovation and impact. Additionally, the committee focuses
on communication, dissemination, and building innovation capacity within the pro-
ject.
- TheWorkPackageleaders and Taskleaders responsiblefor theoverall management
and coordination at WP and Task level and the achievement of the defined results.
Figure 1:REFEST Organizational structure
Section 6oftheConsortium Agreement defines thedetailsofREFESTGovernanceStructure,
thenext paragraphs presentrelevant information forthedevelopmentoftheforeseen activ-
ities.
2.1 PROJECT COORDINATOR
KU, Coordinator of REFEST Project, shall be the intermediary between the Parties and the
GrantingAuthorityandshallperformalltasksassignedtoitasdescribedintheGrantAgree-
ment and in the Consortium Agreement.
KU is in charge of the overall administrative management of the project, being the single
point of contact with the European Commission (EC). KU is responsible for the execution of
the administrative and financial activities of the GA; it is also in charge of ensuring effective
communication, collaboration and cooperation within the Consortium by defining docu-
ment, reporting and control procedures.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page13
The Coordinator shall be responsible for:
• Monitoring compliance by the Parties with their obligations.
• Keeping the address list of Members and other contact persons updated and availa-
ble.
• Collecting, reviewing to verify consistency, and submitting reports, other delivera-
bles(includingfinancialstatementsandrelatedcertifications)andspecificrequested
documents to the Granting Authority.
• Preparingthemeetings,proposingdecisionsandpreparingtheagendaoftheGeneral
Assembly meetings, chairing the meetings, preparing the minutes of the meetings,
and monitoring the implementation of decisions taken at meetings.
• Transmitting promptly documents and information connected with the Project to
any other Parties concerned.
• Administering the financial contribution of the Granting Authority and fulfilling the
financial tasks described in Section 7.2 of the Consortium Agreement.
• Providing, upon request, the Parties with official copies or originals of documents
that are in the sole possession of the coordinator when such copies or originals are
necessary for the Parties to present claims.
• If one or more of the Parties are late in submission of any project deliverable, the
Coordinator may nevertheless submit the other Parties’ Action deliverables and all
other documents required by the Grant Agreement to the Funding Authority in time.
• The Coordinator shall not enlarge its role beyond the tasks specified in this Consor-
tium Agreement and in the Grant Agreement.
• The Coordinator shall not be entitled to act or to make legally binding declarations
on behalf of any other Party or of the Consortium.
Responsible partner: KU
2.2 GENERAL ASSEMBLY
The General Assembly consists of one representative of each Party (Member).
Each Member shall be deemed to be duly authorised to deliberate, negotiate and decide on
all matters listed in Section 6.3.7 of this Consortium Agreement and summarized below:
The General Assembly, shall be free to act on its own initiative to formulate proposals and
take decisions in accordance with the procedures set out herein.
The Coordinator shall chair all meetings of theGeneral Assembly, unless decided otherwise
by the General Assembly.
The Parties agree to abide by all decisions of the General Assembly.
This does not prevent the Parties from exercising their veto rights, according to Section
6.3.5, or from submitting a dispute for resolution in accordance with the provisions of set-
tlement of disputes in Section 11.8 of this Consortium Agreement.
The following decisions shall be taken by the General Assembly:
Content, finances and intellectual property rights.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page14
- Proposals for changes toAnnexes 1 and 2oftheGrant Agreement tobeagreed bythe
Granting Authority.
- Changes to the Consortium Plan.
- Modifications or withdrawal ofBackground in Attachment 1 (Background Included)
- Additions to Attachment 3 (List of Third Parties for simplified transfer according to
Section 8.3.2) of the CA.
- Additions to Attachment 4 (Identified entities under the same control)of the CA.
Evolution of the consortium.
- Entry of a new Party to the Project and approval of the settlement on the conditions
of the accession of such a new Party.
- Withdrawal of a Party from the Project and the approval of the settlement on the
conditions of the withdrawal.
- Proposal to the Granting Authority for a changeof the Coordinator.
- Proposal to the Granting Authority for suspension of all or part of the Project.
- Proposal totheGranting Authorityfor termination oftheProject and theConsortium
Agreement.
Breach, defaulting party status and litigation.
- Identification of a breach by a Party of its obligations under this Consortium Agree-
ment or theGrant Agreement.
- Declaration of a Party to be a Defaulting Party.
- Remedies to be performed by a Defaulting Party.
- TerminationofaDefaulting Party’s participation in theconsortium and measures re-
lating thereto.
- Steps to betaken for litigation purposes and thecoverageoflitigation costs in caseof
joint claims of the parties of the consortium against a Party (Article 7.1.4 of the CA).
In the case of abolished tasks as a result of a decision of the General Assembly, Members
shallrearrangethetasks oftheParties concerned.Sucharearrangement shalltakeinto con-
sideration any prior legitimate commitments which cannot be cancelled.
Responsible partner: KU
Members: one per partner
Frequency of the meetings: at least twice per year
2.3 TECHNICAL & STEERING COMMITTEE
The Technical Steering Committee (TSC) is composed of onemember from each partner or-
ganization and plays a crucial role in overseeing the technical progress and quality of the
project. Its primary responsibility is to review deliverables, ensuring they meet the stand-
ards and requirements, following the methodology detailed in Section 5.
Through regular assessments andfeedback,the committeemaintains theproject'stechnical
integrity and drives its successful execution.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page15
Responsible partner: RISE
Members: one per WP leader
Frequency of the meetings: At least quarterly
2.4 EXECUTIVE BOARD
The Executive Board (EB) plays a crucial role in the strategic management of the project,
ensuring alignment with overall objectives and timelines. Led by AIMPLAS, the EB supports
thecoordinator inpreparingtheconsortiummeetings,which areheldtwiceayear.One-two
months before each consortium meeting, the EB convenes to conduct an overview of the
project, identifying critical points for the next six months. During these meetings, they re-
view the Grant Agreement to ensure that all necessary aspects are clearly understood and
can be completed on time.
Additionally, the EB helps identify the most relevant issues to be discussed at the in-person
meetings, ensuring they are effective and focused on the project’s key objectives. This pro-
active approach not onlyaddresses challenges effectivelybut also drives theoverallsuccess
of the project.
Responsible partner: AIMPLAS
Members: KU, CALSENS, TUCO, LFPA
Frequency of the meetings: at least twice per year
2.5 INNOVATION COMMITTEE
The Innovation Committee plays a pivotal role in managing the innovation process within
the project, ensuring that it progresses smoothly and effectively. This involves overseeing
stakeholder engagement, which is crucial for fostering collaboration and leveraging diverse
perspectives to facilitate innovation and maximize impact.
In addition to managing these engagements, the Innovation Committee places a strong em-
phasis on communication and dissemination. It ensures that innovative outcomes and
knowledge are effectively shared both within the project team and with external audiences,
promoting transparency and encouraging the adoption of project results.
Responsible partner: ENCO
Members: LFPA
Frequency of the meetings: at least twice per yearAll RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page16
2.6 WORK PACKAGE LEADER
Each Work Package has a designated Work Package Leader responsible for:
- Coordinating his/her WorkPackages tasks withand among theParties and potential
third parties participating in those tasks.
- Ensuring the quality control of the said Parties contributions.
- Gathering thesecontributionstopreparethecorrespondinghigh-qualityWorkPack-
age deliverables and milestones.
- Dealing with all issues concerning theprovisionofhigh-level services asdescribed in
Annex I of the Grant Agreement.
- Monitoring all Project activities in order to have regularly an up-to-date idea of state
of progress of the Project, the performance of the concerned Parties and potential
third parties responsible for the activities of the Work Package.
- Where appropriate, suggest the Technical and Steering Committee changes and ad-
justmentstotheoriginalWorkPlanand/orConsortiumPlanatanytimedeemednec-
essary.
- If deemed necessary, handle any disagreement that may arise among the Parties in-
volved in their Work Package(s) regarding the implementation of the Project.
- Being responsible for reporting on Work Packages led to the Commission, including
requesting partner inputs as necessary.
WP number WP Partner
WP1 MIR
WP2 CALSENS
WP3 ELKON
WP4 BLUENAV
WP5 TUCO
WP6 RINA-C
WP7 LFPA
WP8 KU
Table 2: WPs leaders
2.7 TASK LEADER
Taskleadersareresponsiblefortheexecutionandoverallcoordinationofthetasksassigned
to them in the implementation plan. Furthermore, each Task Leader is responsible for the
coordination of the partners involved in the task and quality control of the activities carried
out by the said partner.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page17
3. COMMUNICATION PROCEDURES
REFEST consortium is using asetoftoolsto ensuretheproper communication and manage-
ment of the project. An online workspace has been created using TEAMS/SHAREPOINT, ac-
cessible through the project website and through TEAMS/SHAREPOINT account using this
link: link. All the members of the consortium received the invitation to join the team.
3.1 CONTACTS LIST
An excel file has been shared among the partners to collect all name, surname, emails of the
team and also their involvement in the different WPs in order to smoothly send different
emails totherightperson.Throughtheexcelfile,partnerscan selectpersonsinvolvedinthe
different WPs/activities and contact them. The list is organized as reported below:
- General Assembly
- Technical & Steering Committee
- Executive Board
- Innovation Committee
- WP7
The contact list is continuously updated by each partner, any modification to the access on
TEAMS/SHAREPOINT is notified to the Project Coordinator (PC), in charge of adding/re-
moving new persons.
To ensure all the emails are processed by each partner, when an email is sent the reference
“REFEST” must be included before any other text in the subject line. The PC should be in-
cluded in any email regarding the progress of the project.
For anyexternal communication,thePCis thecontact pointwiththefunding authority– the
EuropeanResearchExecutiveAgency(REA)andhewilltakeregularcontactwiththeProject
Officer by email, the Funding & Tender Portal and using any other communication means
(e.g. telephone).
3.2 PROJECT REPOSITORY
REFEST TEAMS/SHAREPOINT folder is associated to the SharePoint, the repository is man-
aged by PC and ENCO.
Different folders have been created to manage and collect all the documents per type and
category. Below the list of existing folders:
- Administrative documents
- Deliverables submitted
- Events
- General
- Meetings
- Periodic Reports
- Risk Management Register
- Synergies
- TemplatesAll RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page18
- WP1
- WP2
- WP3
- WP4
- WP5
- WP6
- WP7
- WP8
- …
The private TEAMS/SHAREPOINT folder is also used for online meetings and short and im-
mediate communications through the chat.
TEAMS/SHAREPOINT also ensures the quality control of all the activities considering this
tool includes the recording of the meetings and the attendance register.
3.3 MEETINGS
Regular meetings are planned to monitor the project progresses, review the achievements,
discuss on technical aspects, and solve any potential issue it may occur during the project
execution.
Any Member:
- Should be present or represented at any meeting;
- May appoint a substitute or a proxy to attend and vote at any meeting;
- And shall participate in a cooperative manner in the meetings.
Article 6.3.2 of the CA defines time and notice of each meeting, the table is also reported
below:
Ordinary meeting Extraordinary Meeting
General Assembly At least twice a year At anytime upon request oftheSteering
Committeeor 1/3 oftheMembers ofthe
General Assembly
45 calendar days 15 calendar days
Executive Board At least twice a year
1-2 months before Gen-
eral Assembly
AtanytimeuponrequestofanyMember
of the Steering Committee
Technical & Steering
Committee
At least quarterly AtanytimeuponrequestofanyMember
of the Steering Committee
Innovation committee At least twice a year AtanytimeuponrequestofanyMember
of the Innovation Committee
Table 3: Time and noticeof the meetings
In addition to themeetingslisted below,WPs and tasks leaders can plan and organizemeet-
ings as many times as needed during the project in presence or via TEAMS/SHAREPOINT.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page19
All the materials: agenda, attendance list, minutes, registration of the meetings will be up-
loaded on TEAMS/SHAREPOINT in order to inform all the partners.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page20
4. DECISION MAKING PROCEDURES
Any decision is taken following a 5-step process:
1. Identification of the topic/decision: once a decision must be taken, the partner in-
volved identify the decision and tentative alternatives.
2. Communication to the project coordinator and the decision-making partners.
3. Analysis of the decision, after having analysed alternatives and impacts.
4. Take action.
5. Review the decision taken and its real impacts.
Meetings and decision procedures, voting rules and quorum, veto rights to be followed as
descried in CA Section 6.
Settlement of disputes among the parties are defined in CA Article 11.8All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page21
5. 5. 5. 5. QUALITY CONTROL QUALITY CONTROL QUALITY CONTROL QUALITY CONTROL
In this section both the quality check of the deliverables and the quality control of the activ-
ities to be developed during the project lifetime and are explained to ensure that all the ex-
pected outcomes are met as well as the consistency of the project outputs.
5.1 QUALITY CONTROL OF THE DELIVERABLES
Deliverables aretheresultsoftheactivities carried out during theproject execution,includ-
ing REFEST’s results and progress. Type and Dissemination level are defined in the DoA,
however they shall be understandable for non-technical people, easy to read and complete;
including as many information as possible related to the activities carried out, results
achieved and impacts.
Each deliverable must include the following elements:
- Cover page
- Quality checklist
- Document details
- Disclaimer ofwarranties
- History of changes, authors, and reviewers
- Table of content
- Executive summary
- List of abbreviations and acronyms
- Introduction
- Conclusions
- Deviations
- Annex (if any)
The content of each deliverable varies according to the activities carried out per task.
A Deliverable Template has been uploaded on TEAMS/SHAREPOINT and is included as An-
nex 1 of this document.
The language used is always British English.
To ensure a good quality and uniformity of each deliverable, a review process has been de-
fined, including timing and responsible partner in charge of the review.
- 45 days before the official submission deadline: the lead beneficiary responsible for
the deliverable must circulate the ToC.
- 30 days before the official submission, the lead beneficiary responsible for the deliv-
erablemust send theconsolidated version (v0.1)ofthedeliverableto theWPleader.
- 21 days before theofficial submission, the WP leader sends his/her comments to the
lead beneficiary responsible for the deliverable.
- 14 days before the official submission, the lead beneficiary responsible for the deliv-
erable send the consolidated version (v0.2) of the deliverable to the reviewer.
- 7daysbeforetheofficialsubmission,thereviewersendshis/hercommenttothelead
beneficiary responsible for the deliverable.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page22
- 3 days before the official submission, the lead beneficiary responsible for the deliv-
erable sends the final version (v0.3) to the PC for the last revision.
- Before the deadline is reached, the PC submits the deliverable through the Funding
& tender Portal.
The timeline, responsible partners and reviewers have been included in the Annex 3 of this
deliverable: REVIEW MATRIX. The Matrix is also available on TEAMS/SHAREPOINT.
To facilitate the exchanges of files and information among partners, a dedicated folder has
been created on TEAMS/SHAREPOINT – WP folder - DELIVERABLES. The partner in charge
ofthedeliverables,the WPleader and thereviewers will upload each version ofthedeliver-
able in this folder, also to give the opportunity to the other partners to read and comment
the deliverable if needed.
The final submitted version of each deliverable will be uploaded to the repository on
TEAMS/SHAREPOINT.
AllpublicdeliverableswillbeuploadedontheprojectwebsiteandonTEAMS/SHAREPOINT
in directory “Deliverables submitted”.
During the review process it is mandatory to use track changes.
The following criteria must be met per each deliverable:
1. Relevance & Accuracy: always include the respective references, to use a language
andastructureinlinewiththetargetaudience.Useofthedefinedtemplateto ensure
uniform appearance.
2. Completeness:includereliable,real and completeinformation;clearlyexplaining the
work done and results achieved.
3. Added value: to include relevant information, that will create a value and potential
impacts for the readers.
4. Clarity: to avoid any spelling errors and to not disclose any sensitive information.
5. Language: use of British English.
6. Timing:respect the internal and official deadlines.
7. Disclaimer: always include references to the EUfunds.
5.2 PROJECT MONITORING AND REPORTING
Two levels of monitoring and reporting will be followed by REFEST consortium to ensure
the project will successfully deliver all the outcomes and expected results.
The first level is at internal way, done by the PC with the support of each WP leader to con-
stantly review all the progress made by the consortium in carrying out the activities. An in-
ternal review is foreseen at M10, linked with the release of the second tranche of the first
pre-financing.
The second level is the official one foreseen in REFEST GA with the REA (PO and external
reviewers).Externalreviewerstobeinvolvedinthereviewwillbeexpertsspecializedinthe
topic of the project and will be proposed by thePO.
All due considered, three types of reporting arerequired:
1. Internal Interim Report at M10.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page23
2. Continuous reporting,through deliverables submission,milestones,risks monitoring,
publications, results,dissemination and communication activities, standards, IPR, da-
tasets, impacts, other results.
3. Periodic reports at M18 and M36
M10internalinterimreportwillensuretheprojectisprogressingwellintermsofdeadlines,
activities and results. The information collected will be also used to complete the Periodic
Report.
Twoofficial reporting periodshavebeen defined intheGA.Thefirstreportingreportwill be
submitted not later than 60 days after the end of the reporting period 1 corresponding to
M1 – M18. The2nd reporting period correspond to the end of the project - M36.The official
report will be submitted 60 days after the end of the reporting period 2 corresponding to
M19 - M36.
The periodicreports consist of:
- Technical Part contribution
- Status of WP
- Project Summary for Publications
Per each reporting period a financial statement is also required, containing lump sum con-
tributions as indicated in theAnnex2 oftheGA,for theWPs that werecompleted during the
reporting period. For the last reporting period, the beneficiaries may exceptionally also de-
clare partial lump sum contributions for WPs that were not completed (e.g. due to force
majeure or technical impossibility). Lump sum contributions which are not declared in a
financial statement will not be taken into account by the granting authority.
5.3 POTENTIAL DELAYS AND CORRECTIVE ACTIONS
If any potential delay will occur, the responsible partner must inform the PC in due time
explaining the reason of the delays and corrective actions.
Any potential risks, deviations, corrective actions must be reported to the PC who will be in
charge of solving potential issues also by informing the PO.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page24
6. 6. 6. 6. RISKS MANAGEMENT RISKS MANAGEMENT RISKS MANAGEMENT RISKS MANAGEMENT
A planned and controlled approach to therisksmanagement is an imperative and indispen-
sable step to ensure the correct execution and delivery of the project results and expected
outcomes.
Risks may affect in a positive or negative way the project and it is really important to define
a strategy and contingency plan to avoid potential negative effects.
This section summarizes REFEST Risk Management Plan to constantly monitor potential
risks and the effects they could have on the project.
A list of risks has been defined during the proposal writing stage, it has been revised and
implementedduring theGAPphaseand included in theDoA.Acontinuousmonitoringofthe
risks will be done during the project execution, revising and updating them if needed.
A Risk Management Register has been implemented and updated on TEAMS/SHAREPOINT,
it has been also included as Annex 4 to this deliverable. The final aim of the register is to
record and monitor all possible risks and any subsequent actions required. On the base of
the Risk Management Register the Risk identification report will be prepared with the due
date of M9.
Per each identified risk, a mitigation measure has been provided including the likelihood
and severity of each risk.
In the first version of the Risk Management Register the degree of criticality and the proba-
bility of risk happening have been included, assigning per each risk a grade. During the pro-
ject execution and risks monitoring the success of intervention will be monitored.
WPleaders areresponsiblefor monitoring therisks related to their WP,everypartner must
notifyanypotentialrisktotherespectiveWPleaderinordertodefinepotentialcontingency
plan to mitigate the risk.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page25
7. 7. 7. 7. CONCLUSIONS CONCLUSIONS CONCLUSIONS CONCLUSIONS
Deliverable8.1containsREFESTProjectManagementPlan.Thisreportaimstoactasaguid-
ance for the 14 consortium partners of REFEST to understand the project structure, imple-
mentation phases and procedures.
Thefinal aim ofthis Deliverableis to give amanagement structureto theentireconsortium,
with activities,deadlines,and templates to befollowed and used when preparing theofficial
reports.
Each WP leader, partner, or team, will further develop their methods and strategies to ex-
changeinformation and facilitatetheinteraction ofactivities,alwaysusing this document as
a baseline.
As mentioned above, D8.1 complements the Grant Agreement and Consortium Agreement
of REFEST and should be used in conjunction with these two documents.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page26
8. 8. 8. 8. DEVIATIONS DEVIATIONS DEVIATIONS DEVIATIONS
This deliverable has been provided according to timeline with no major deviations.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page27
ANNEX 1 ANNEX 1 ANNEX 1 ANNEX 1 – – – – DELIVERABLE TEMPLATE DELIVERABLE TEMPLATE DELIVERABLE TEMPLATE DELIVERABLE TEMPLATE
The Deliverable template is available on TEAMS/SHAREPOINT at the following link.All RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST | D8.1 (v1) Project Management Plan | Page28
ANNEX 2 ANNEX 2 ANNEX 2 ANNEX 2 – – – – POWER POINT TEMPLATE POWER POINT TEMPLATE POWER POINT TEMPLATE POWER POINT TEMPLATE
The PowerPoint template is available on TEAMS/SHAREPOINT at the following link.“This project has receivedfunding from the EuropeanUnion’s HorizonEuropeResearchand Innovation ProgrammeunderGrant AgreementNo.101157663. Views and opinions expressed
are however those of the author(s) only and do not necessarily reflect those of the European Union or the European Climate, Infrastructure and Environment Executive Agency (CINEA).
Neither the EuropeanUnionnor the granting authority canbe held responsiblefor them”
ANNEX 3 ANNEX 3 ANNEX 3 ANNEX 3 - - - - DELIVERABLES REVIEW MATRIX DELIVERABLES REVIEW MATRIX DELIVERABLES REVIEW MATRIX DELIVERABLES REVIEW MATRIX
Deliverable
No
Del. Re-
lated
No
Deliverable Name WP Leader Type
Diss.
Level
Due Date Review Date Reviewer
D1.1 D1
Requirements for materials, compo-
nents, and demo-ships WP1 KU R PU 31 Jan 2025 24 Jan 2025 TSC
D1.2 D2
Report of impact assessment of marine
environment WP1 MIR R PU 30 Apr 2026 23 Apr 2026 TSC
D1.3 D3
Report of impact assessment ofBaltic &
North Sea biodiversity WP1 MIR R PU 31 Mar 2027 24 Mar 2027 TSC
D2.1 D4
Designs of hull appendages for the
demo-ships WP2 KU R SEN 31 Oct 2025 24 Oct 2025 TSC
D2.2 D5
Standardization and modularization of
the appendage designs WP2 KU R PU 31 Jan 2026 24 Jan 2026 TSC
D2.3 D6
Report of thermoplastic composites for
hull appendages WP2 AIMPLAS R PU 31 Oct 2025 24 Oct 2025 TSC
D2.4 D7
Report of manufacture of fibre-optic
multi-sensors WP2 CALSENS DEM SEN 31 Oct 2025 24 Oct 2025 TSC
D2.5 D8
Report of integration of fibre-optic sen-
sors in composites WP2 AIMPLAS DEM PU 31 Jan 2026 24 Jan 2026 TSC
D3.1 D9
Report of ship energy efficiency on elec-
trical architecture WP3 ELKON R SEN 31 Oct 2025 24 Oct 2025 TSCAll RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST| D8.1 (v1)Project ManagementPlan|Page
30
Deliverable
No
Del. Re-
lated
No
Deliverable Name WP Leader Type
Diss.
Level
Due Date Review Date Reviewer
D3.2 D10
Report of data driven PMS & EMS devel-
opment WP3 ELKON R PU 31 Jan 2026 24 Jan 2026 TSC
D3.3 D11
Report on battery cell selection and elec-
trical model WP3 EAS R PU 31 Jan 2025 24 Jan 2025 TSC
D3.4 D12
Summary report of cell characterization
and BMS parameters WP3 EAS R PU 31 Jul 2025 24 Jul 2025 TSC
D3.5 D13
Report on mechanical design for batter-
ies for cold weathers WP3 KU R PU 31 Oct 2025 24 Oct 2025 TSC
D3.6 D14
Report of composites from thermoplas-
tics and synthetic fibres for battery box.
Materials datasheet.
WP3 AIMPLAS R PU 31 Oct 2025 24 Oct 2025 TSC
D3.7 D15
Modification of flexible PV panels for
their integration in ships WP3 NXH DEM PU 31 Jan 2026 24 Jan 2026 TSC
D4.1 D16 Report of eco-driving solutions WP4 BLUENAV R PU 31 Oct 2025 24 Oct 2025 TSC
D4.2 D17
Report of RIM engine power increase
and localization WP4 BLUENAV DEM PU 31 Jan 2026 24 Jan 2026 TSC
D4.3 D18
Report of Air lubrication system meth-
ods and designs WP4 RISE R PU 31 Oct 2025 24 Oct 2025 TSC
D4.4 D19
Report of Air lubrication system compo-
nent design WP4 RISE R SEN 31 Jan 2026 24 Jan 2026 TSCAll RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST| D8.1 (v1)Project ManagementPlan|Page
31
Deliverable
No
Del. Re-
lated
No
Deliverable Name WP Leader Type
Diss.
Level
Due Date Review Date Reviewer
D4.5 D20
Standardization & modularization of the
air-lubrication designs WP4 RISE R PU 31 Oct 2025 24 Oct 2025 TSC
D4.6 D42
Update of Standardization & modulariza-
tion of the air-lubrication designs WP4 RISE R PU 31 Mar 2027 24 Mar 2027 TSC
D5.1 D21
Report of scale-up the production of re-
quired materials and parts for the target
retrofitting solutions.
WP5 TUCO R PU 31 Oct 2026 24 Oct 2026 TSC
D5.2 D22
Report of scale-up the manufacture aux-
iliar retrofitting solutions WP5 NXH R PU 31 Oct 2026 24 Oct 2026 TSC
D5.3 D23
Retrofitting solutions implemented in
each ship WP5 TUCO R PU 31 Oct 2026 24 Oct 2026 TSC
D5.4 D24
Demonstrators: three ships with new
retrofitting solutions WP5 TUCO DEM PU 30 Apr 2027 23 Apr 2027 TSC
D5.5 D25
Report of main drawbacks detected and
the improvement proposals in the short
and medium term
WP5 LFPA R PU 30 Apr 2027 23 Apr 2027 TSC
D5.6 D26
Holisticdecommissioning, and recycling
studyof components WP5 AIMPLAS R PU 31 Mar 2027 24 Mar 2027 TSC
D6.1 D27 Report of LCA/LCC assessment WP6 RINA-C R PU 31 Jan 2027 24 Jan 2027 TSC
D6.2 D28 Report of SLCA assessment WP6 RINA-C R PU 31 Jan 2027 24 Jan 2027 TSC
D6.3 D29 Report on H&S assessment WP6 RINA-C R PU 31 Jan 2027 24 Jan 2027 TSCAll RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST| D8.1 (v1)Project ManagementPlan|Page
32
Deliverable
No
Del. Re-
lated
No
Deliverable Name WP Leader Type
Diss.
Level
Due Date Review Date Reviewer
D6.4 D30
Report on toxicological and safety as-
pects WP6 AIMPLAS R PU 31 Mar 2027 24 Mar 2027 TSC
D6.5 D31 Regulatory gap assessment report WP6 RINA-C R PU 31 Mar 2027 24 Mar 2027 TSC
D7.1 D32
Communication Toolkit, Public website
& Social Media groups WP7 ENCO R PU 31 Jul 2024 26 Jul 2024 TSC
D7.2 D33 Update of Policy recommendations WP7 RINA-C R PU 28 Feb 2027 21 Feb 2027 TSC
D7.3 D34
Plan for Dissemination, Exploitation,
Communication PDEC WP7 ENCO R PU 31 Oct 2024 24 Oct 2024 TSC
D7.4 D35 Business Model and Business Plan WP7 ENCO R SEN 31 Oct 2025 24 Oct 2025 TSC
D7.5 D36 Policy recommendations WP7 RINA-C R PU 31 Oct 2025 24 Oct 2025 TSC
D7.6 D37 Data Management Plan WP7 ENCO DMP PU 31 Oct 2024 24 Oct 2024 TSC
D7.7 D40 Clustering activities report WP7 ENCO R PU 31 Mar 2027 24 Mar 2027 TSC
D7.8 D41
Data Management Plan – updated ver-
sion WP7 ENCO DMP PU 31 Oct 2025 24 Oct 2025 TSC
D7.9 D43 Data Management plan final version WP7 ENCO DMP PU 31 Mar 2027 24 Mar 2027 TSC
D7.10 D44
Update of Business Model and Business
Plan WP7 ENCO R SEN 31 Mar 2027 24 Mar 2027 TSC
D8.1 D38 Project Management Plan WP8 KU R PU 31 Jul 2024 26 Jul 2024 TSC
D8.2 D39 Risk identification – KU in– public report WP8 KU R PU 31 Jan 2025 24 Jan 2025 TSCAll RightsReserved. REFESTProject. Grant Agreement 101157663.
REFEST| D8.1 (v1)Project ManagementPlan|Page
33
ANNEX 4 ANNEX 4 ANNEX 4 ANNEX 4 – – – – RISK MANAGEMENT REGISTER RISK MANAGEMENT REGISTER RISK MANAGEMENT REGISTER RISK MANAGEMENT REGISTER
Risk
number
Description WP
Degree of critical-
ity of the risk
(1 low- 10 high)
Probability of
risk happening
(1 low - 10 high)
Proposed Mitigation
Measures
Estimated Feasibility /
Success of Intervention
(1 low- 10 high)
ConclusionIdentifikace uložené verze